This article was co-authored with Jack Brown and Nishta Gupta.
Norton Rose Fulbright provides a monthly overview of the key updates to Australian East Coast energy regulation.We have curated this list for the key updates. There may be others relevant to your business. To view our previous instalment, please click here.
| Update | Amended or Governing Instrument(s) | Application | Status |
| Australian Energy Regulator (AER) releases updated Capital Expenditure Incentive Guidelines |
Capital Expenditure Incentive Guidelines | National Electricity Market – distribution and transmission | Capital Expenditure Incentive Guidelines are effective from 4 September 2025. |
|
Description: The Australian Energy Regulator (AER) has published its final updated Capital Expenditure Incentive Guidelines (Guidelines). These Guidelines outline the ex-ante and ex-post measures to incentivise efficient capital expenditure for networks. The updates address:
These amendments were aimed at ensuring that the measures to incentivise efficient capital expenditure remain fit for purpose by enabling sufficient flexibility, without undermining the existing design and robustness of the schemes. |
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| AER is increasing the minimum disconnection amount from 1 July 2026 |
National Energy Retail Rules | National Electricity Customer Framework | The increased minimum disconnection amount will take effect from 1 July 2026. |
| Description: The AER has published the final decision from its Review of the minimum disconnection amount. It has decided to increase the minimum disconnection amount from $300 to $500 (including GST). The amount applies to both electricity and gas customers. The minimum disconnection amount is the minimum amount that must be outstanding before a customer can be disconnected for non-payment of a bill, provided that the customer has agreed with their retailer to repay the amount. |
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| AER releases PASA Compliance Bulletin and Checklist |
Projected Assessment of System Adequacy Compliance Bulletin | National Electricity Market – wholesale | The PASA Compliance Bulletin and Checklist was published on 29 August 2025. |
|
Description: The AER has released guidance for electricity market participants outlining its expectations regarding compliance with critical Projected Assessment of System Adequacy (PASA) obligations under the National Electricity Rules (NER). PASA is used to indicate to the Australian Energy Market Operator (AEMO) and market participants the forecast of overall balance of supply and demand for electricity in the National Electricity Market (NEM). The new PASA Compliance Bulletin refreshes the AER’s expectations around PASA compliance that were previously included as part of the AER’s NEM Readiness Guide. The new standalone Bulletin focuses on PASA obligations and relevant updates for participants to be aware of, while the checklist sets out tasks that may assist participants to achieve compliance.
|
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| AER publishes Embedded Network Review Final Decision |
Network Exemptions Guideline and Retail Exempt Selling Guideline | National Electricity Market – electricity and gas – distribution, retail | The final decision for the Embedded Network Review was published on 29 August 2025. The revised Network Exemptions Guideline and Retail Exempt Selling Guideline have new requirements and protections that take effect throughout 2026 (see details in the column to the left). |
|
Description: The AER has published the revised Network Exemptions Guideline and Retail Exempt Selling Guideline (versions 7), alongside the final decision for its review of the exemptions framework for embedded networks.6 The AER commenced its review to better understand the benefits, harms and risks embedded network customers may be facing and whether any action is needed, including whether the AER should restrict the growth of residential embedded networks via our Network Exemptions Guideline. They released an issues paper in November 2023, and a draft decision in March 2025. The guidelines published include several new conditions or measures to address the issues identified through the review. These include:
The final decision acknowledges that all energy customers should have a comparable level of consumer protections, to the extent possible, regardless of their energy supplier. |
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| AER publishes final decision to update the interim Contracts and Firmness Guidelines 2025 |
Contracts and Firmness Guidelines | National Electricity Market – retail, wholesale | Submissions ahead of the planned review of the interim Contracts and Firmness Guidelines in 2026 are open to the AER. |
| Description: The AER published its final decision on 20 August 2025 to amend the interim Contracts and Firmness Guidelines for the Retailer Reliability Obligation (RRO) to reflect a recent rule change to the National Electricity Rules (NER). The interim Contracts and Firmness Guidelines are one of 6 guidance documents that set out how the AER exercises its functions under the RRO. When the RRO is triggered, retailers (and any large customers who opt-in) are required to hold sufficient electricity contracts to meet their share of demand. The interim Contracts and Firmness Guidelines set out how to report on these contracts to the AER. In 2026, the AER will conduct a broader review of the interim Contracts and Firmness Guidelines. Under this review, it will consider integrating price-responsive resources into the NEM Rule 2024 No. 24 rule change alongside a broader range of matters. The interim Reliability Instrument Guidelines and interim Market Liquidity Obligation Guidelines will also be updated alongside the interim Contracts and Firmness Guidelines, with the aim to finalise all 3 guidelines in 2026. |
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| Electricity Infrastructure Investment Amendment (Priority Network Projects) Act 2025 (NSW) |
Electricity Infrastructure Investment Act 2020 (NSW) | NSW – electricity – generation, transmission and distribution | This amendment commenced on 13 August 2025. |
|
Description: The Electricity Infrastructure Investment Act 2020 (NSW) (EII Act) was amended on 13 August 2025 to:
|
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| Energy (Renewable Transformation and Jobs) (Transmission Ring-fencing Rule) Amendment Regulation 2025 (Qld) |
Energy (Renewable Transformation and Jobs) Regulation 2024(Qld) | Queensland transmission | The amended regulation commenced on 24 August 2025. |
| Description: The Energy (Renewable Transformation and Jobs) Regulation 2024 (Qld) was amended to explicitly apply the Transmission Ring-fencing Rule to Powerlink and harmonise state and national frameworks. |
|||
| Update | Amended or Governing Instrument(s) | Application | Status |
| Victorian Energy Efficiency Target (Project-Based Activities) Amendment Regulations 2025 (Vic) |
Victorian Energy Efficiency Target (Project-Based Activities) Regulations 2017 (Vic) | Victoria – gas – retail and customer | The amended regulation commenced on 26 August 2025. |
|
Description: The regulation amends the Victorian Energy Efficiency Target (Project-Based Activities) Regulations 2017 (Vic) to:
|
|||