2026 will be a big year for building reform in Victoria, with three packages of reforms due to commence between 1 July and 1 December 2026. The Building Legislation Amendment (Buyer Protections) Act 2025 (Vic) (Act) will be the first to commence, on 1 July 2026.The other two packages are the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 (Vic), expected to commence 1 September 2026, and the Domestic Building Contracts Amendment Act 2025 (Vic), expected to commence 1 December 2026.

The Victorian Government (VicGov) has taken the next step towards implementing the Act, with the release of draft regulations to support the Act and a regulatory impact statement. Its consultation process is open until 30 January 2026.

As set out in our previous updates, the Act introduces a new statutory insurance scheme (SIS) for low rise residential buildings, a new developer bond scheme for multi-storey residential buildings and expands rectification powers, significantly reshaping building regulation in Victoria. You can read our previous updates here and here.

VicGov has split the regulations to support the Act into three separate documents. This update focuses on the exposure draft regulations to support the developer bond scheme.

The developer bond scheme for multi-storey residential buildings (four storeys or more) is modelled on the New South Wales Strata Building Bond and Inspection Scheme. It will protect building owners by requiring developers to provide a developer bond of 2 per cent of the total build cost, which an owners corporation can apply to access to rectify defects identified in inspections conducted 15-18 months and 21-24 months after the occupancy permit for the building is issued.

The draft Building (Developer Bonds) Regulations 2025 (Vic) provide us with VicGov’s proposed answers to some issues that were not fully detailed in the Act:

  • Transitional provisions – the draft regulations propose that a developer will be exempt from the requirement to provide a developer bond if the relevant building permit was issued before 1 July 2027. The proposed approach will enable developers to set up contractual arrangements for future projects with a clear understanding about whether a developer bond will be required.

  • Exempted project types – the draft regulations propose that developers of certain project types will be exempt from the requirement to provide a developer bond:

    • BTR (build-to-rent) developments that meet the eligibility requirements for tax concessions.
    • Public and community housing developments (social housing), except where the development has residential lots that are to be sold off to the private market.
  • Building assessor qualifications – to be appointed as a building assessor to carry out inspections under the scheme a person will need to be a registered domestic builder (unlimited), building inspector (unlimited) or building surveyor (unlimited), but the Building and Plumbing Commission (BPC) will have discretion to approve the qualifications of other individuals as well.

  • Reportable defective building work – the types of defects that building assessors must identify and report on, and for which claims on a developer bond can be made if the issues are not rectified are proposed to be:

    • Defective building work (broadly defined as a breach of a warranty in s8 of the Domestic Building Contracts Act 1995 (Vic) or a failure to maintain a standard or quality of building work specified in the domestic building contract) in the common property or a private residential lot of a residential apartment building.
    • Serious defects in any other building work in a residential apartment building (for example a cafe, shop or office space in a multi-use development).
  • Total build cost – the “total build cost” (from which the 2 per cent bond is calculated) will align with the total cost of building work reported by the relevant building surveyor for determining the building permit levy payable. However, a deduction will be permitted for the cost of any building work included in the building permit levy calculation but not carried out for or in connection with the construction of the residential apartment building. The BPC will publish guidance to assist with calculating any deduction.

  • Release of developer bond - the proposed regulations prescribe a maximum period that a developer bond must be made available for claims, being 12 months after the assessor’s final report. This period may be extended if an application is made for a decision to be reviewed. This provides developers with certainty over the upper limit of the timeframe for which a bond must be available. In many cases the bond will be released much earlier than this maximum period. On the best-case scenario, if the assessor’s preliminary report (15 to 18 months after the occupancy permit) does not identify any reportable defective building work, then the developer bond will be released as soon as practicable after receipt of that report.

Developers are likely to be reassured by the proposed answers in the draft regulations, particularly the proposed transitional provision which should provide industry with a smooth transition to the developer bond scheme. We will continue to provide updates this year on the implementation of building reform in Victoria.

You can view the draft regulations and participate in the consultation process here.

Footnotes

  1. 1

    The other two packages are the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 (Vic), expected to commence 1 September 2026, and the Domestic Building Contracts Amendment Act 2025 (Vic), expected to commence 1 December 2026.

card-grid-item, aem-sourced
Projects NewsWire Australia
This series includes insights into significant market, policy and project related developments from our highly experienced team.
https://web.nortonrosefulbright.com/Projectnewswiresubscriptionpage

Contact