This article was co-authored with Matt Alvites.
Executive summary
The Environment Protection Reform Act 2025 (Cth) and six related pieces of legislation passed Parliament in November 2025 and received Royal Assent on 1 December 2025 (EPBC Act Reforms).
While some amendments came into effect in December 2025, the majority will commence incrementally throughout 2026. The full suite of changes will come into effect by no later than 1 December 2026, allowing time for the related policy instruments and guidelines to be finalised.
This update discusses the EPBC Act Reforms that came into effect on 20 February 2026 (Tranche 1 Reforms). This update is part of our ongoing guidance on the significant reforms to the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act). Environment Protection Reform Commencement Proclamation (No. 1) 2026 (Cth) (19 February 2026)
Our previous articles on the EPBC Act Reforms can be read hereand here.
Timeline and milestones
The commencement of the Tranche 1 Reforms signals the start of the implementation timeline of the broader EPBC Act Reforms package. The table below shows key dates and milestones related to the commencement of the EPBC Act Reforms.
| Date | Milestone | Key details |
| 28 November 2025 | Legislation passed | Seven-bill reform package passed Parliament. |
| 1 December 2025 | Royal Assent | Legislation received Royal Assent. |
| 30 January 2026 | Draft Standards | Consultation closed on the first two draft Standards: Matters of National Environmental Significance (MNES) and Environmental Offsets. |
| 20 February 2026 | Tranche 1 commences | Initial reforms take effect. |
| 24 March 2026 | Committee Report | Reporting date for the Senate Committee inquiry into the reform package. |
| 1 July 2026 | NEPA & EIA launch | National Environmental Protection Agency (NEPA) and Environment Information Australia (EIA) begin operations. |
| 1 December 2026 (or before) | Full implementation |
The balance of the reforms (Tranche 2) will become operational, including those related to:
|
Below we discuss the Tranche 1 Reforms which are now operational.
Strategic assessments
Strategic assessments under the EPBC Act allow for the approval of an action or a class of actions across a defined area, identifying where and what kind of activities are allowed and what conditions apply. Strategic assessments are currently used in areas such as urban growth and development in Melbourne’s urban growth boundary and Sydney’s growth centres, and for infrastructure covering NSW roads and traffic management works.
The Tranche 1 Reforms have amended the process for strategic assessment of actions taken in accordance with endorsed policies, plans or programs under Part 10 of the EPBC Act so that:EPBC Act ss 146BA, 146CA, 146DC, 146DI
- Conditions of existing strategic assessment approvals can be varied.
- Minor variations to endorsed policies, plans or programs can be made.
When considering strategic assessment approvals, the Minister must consider the principles of ecologically sustainable development, any bioregional plan, and relevant expert scientific advice (where the action involves large coal or unconventional gas projects).Ibid s 146F
The changes to strategic assessments are intended to make them more flexible over time.
National interest exemptions under Part 11
The Tranche 1 Reforms expand the ‘national interest exemption’ under Part 11 of the EPBC Act. The Minister can now impose conditions on the taking of an action covered by a national interest exemption and provide for a set period for the granting of an exemption.Ibid s 157M
National interest exemptions can now be varied, revoked and surrendered either on application, or in some cases, on the Minister’s own initiative. Ibid ss 157P, 157Q, 157S, 157U This is intended to allow for faster and more effective responses to national emergency situations, such as bushfire management.
Information sharing between agencies
The Tranche 1 Reforms include a new regime for the use and disclosure of information obtained or generated under the EPBC Act.
Information collected under the EPBC Act can now be disclosed to:Ibid ss 515C, 515J, 515K
- Other Commonwealth entities.
- State and Territory government bodies.
- To the National EPA or EIA.
The new information sharing arrangements aim to support faster decision making under the EPBC Act and greater availability of environmental information.
Reconsidering ‘particular manner’ decisions
In limited circumstances, the Minister’s decision that an action is not a controlled action can be reconsidered if:
- Substantial new information about impacts becomes available.
- There is a substantial change in circumstances.
As a result of the Tranche 1 Reforms, the Minister can now be asked to reconsider a decision that an action is not a controlled action if taken in a particular manner, if the identified manner is no longer appropriate. Ibid s 79A
Further, following a reconsideration request, certain actions that have been determined to be a controlled action may continue to be taken during the assessment, and the Minister may specify conditions that apply to the taking of the action.Ibid s 79E
Surrender of approvals
The holder of an approval for the taking of an action may now request the Minister to accept the surrender of the approval. Ibid s 145AA
In deciding whether to accept the surrender of the approval, the Minister may consider:
- Whether the taking of the action has “substantially commenced”.
- The risk of the surrender to a protected matter under the EPBC Act for which the approval has effect.
This change allows approval holders to surrender approvals that are not being acted on and thereby reduce their compliance burden.
Indigenous Advisory Committee
The role of the Indigenous Advisory Committee (IAC) has now been expanded to embed First Nations knowledge in environmental governance and decision-making under the EPBC Act.Ibid s 505B(1)
Subject to the commencement of relevant provisions in Tranche 2:
- The IAC will be consulted in the development of a national environmental standard relating to engagement with First Nations peoples.
Ibid s 514YI(1) (not yet in effect) - Listing of threatened species and ecological communities will require the Threatened Species Scientific Committee to provide the IAC with specific documentation relevant to the listing with the intention that the IAC retains visibility of nominations.
Ibid s 194L(3) (not yet in effect)
Wildlife permits
The Tranche 1 Reforms include changes to the permitting of wildlife trade operations under Part 13A of the EPBC Act for the purpose of export of specimens.
The period of operation for declarations that a specified wildlife trade operation is an approved wildlife trade operation has been extended to up to five years. Ibid s 303FN
Next steps
The full suite of EPBC Act Reforms will commence on 1 December 2026, if not proclaimed earlier.
Proponents should start considering whether their environmental approvals are appropriate and reviewing the strength and adequacy of their compliance systems given the increased penalties which will apply under Tranche 2 of the EPBC Act reforms.
In the meantime, the Federal Government has committed to further consultation with stakeholders on the implementation detail. Environment protection reforms - DCCEEW(accessed 23 February 2026) We anticipate that the First Nations Engagement, Community Engagement, and Data and Information Standards will be released for consultation in 2026 along with finalisation of the Standards for MNES and Environmental Offsets; however, no formal timeframe has been confirmed.
There is also work to be done to renegotiate the bilateral agreements between the states and the Federal Government as one of the approval pathways apart from bioregional plans and strategic assessments.
We will continue to publish updates on the EPBC Act Reforms as they progress.