This article was co-written by Angelique Barkas
The Australian Government has released exposure draft legislation for its Domestic Gas Reservation Scheme (Scheme), a significant regulatory framework intended to secure domestic natural gas supply. The draft represents a notable evolution from the May 2026 design framework, shifting from a fixed volume obligation to a more flexible, market-balancing model.
From fixed obligation to ministerial discretion
The centrepiece of the May 2026 framework was a straightforward 20 per cent domestic supply obligation (DSO). The exposure draft softens the headline requirement to up to 20 per cent of export volumes. The actual percentage will be determined by the Commonwealth Resources Minister for each domestic gas market.
This signals a fundamental shift in design philosophy: rather than imposing a universal volume-based compliance model, the scheme now operates as a market-balancing mechanism, with obligations calibrated to maintaining an aggregate domestic supply target of 110 per cent of forecast demand. The Minister retains discretion to lower this target and to set differentiated DSO percentages for the east coast and Western Australian markets.
For an industry built on long-term investment horizons and multi-decade sales contracts, this discretion potentially introduces a new category of regulatory risk. There will be a significant change in forecasting how the Minister and the Australian Energy Regulator (AER) will exercise their respective powers.
Key features of the draft legislation
The Scheme comprises three Bills, with the primary instrument establishing an export licensing regime and the DSO framework.
Export licence
From 1 January 2028, all LNG exporters must hold an export licence (granted for 20–50 years) and meet their calibrated DSO. Critically, the obligation is to supply gas, not just to offer it. Exporters must physically deliver gas into the domestic market, typically under binding contracts or through facilitated markets. An exporter must supply at least 90 per cent of its annual DSO, with up to 10 per cent deferrable across the next three regulatory periods under an "overs and unders" mechanism. This replaces the earlier "release valve" that would have permitted export of surplus DSO volumes. Notably, the removal of the release valve means there is no express mechanism for exporters to redirect unneeded surplus gas to export markets.
Pre-existing contracts
Contracts entered into before 22 December 2025 may be recognised, but relief is not automatic. The Minister must be satisfied that without an adjustment the licence holder would likely breach the contract, that additional gas cannot reasonably be acquired, and that the holder is actively improving its ability to meet the DSO.
Additionality
The additionality framework requires DSO gas to be the licence holder's "own gas" or "additional gas" produced above an AER determined baseline. This is designed to ensure exporters are net contributors to domestic supply, not reallocators of existing volumes. However, the practical detail (including baseline-setting methodology) will be determined by AER subordinate instruments, that have not yet been published.
Role of Regulator
The AER has been given broad powers so they can administer the Scheme. Beyond calibrating the DSO through the demand calibration mechanism, the AER's functions include promoting, monitoring, investigating, auditing and enforcing compliance with the legislation. The AER will also establish production baselines for the additionality framework and will serve as a central point of advisory support to the Minister on matters relating to the Scheme's operation.
Implications for market participants
For LNG exporters
The revised approach offers some comfort that obligations will be responsive to market conditions rather than rigidly applied. However, the breadth of Ministerial discretion, including the power to suspend or cancel licences without compensation, adds a layer of risk. Western Australian exporters face additional uncertainty about how the federal DSO will interact with the state's existing 15% domestic reservation policy, although existing arrangements are a recognised basis for reducing the DSO (subject, again, to Ministerial discretion).
For domestic gas users
The 110% oversupply target signals continued government commitment to supply security. However, forced supply obligations risk flooding the market, potentially suppressing prices below levels that support new upstream investment and crowding out smaller domestic-focused producers.
For investors and financiers
The regime's reliance on periodic Ministerial and AER calibration may prove difficult to model over project life cycles, particularly given the absence of detail on financial assurance requirements.
Next steps
Submissions on the exposure draft close 24 September 2026. The Scheme commences 1 January 2027 to allow licence applications, with DSO obligations taking effect from 1 January 2028. The AER will develop subordinate instruments through 2027. How well the framework balances domestic energy security, investment certainty and a competitive gas market remains the central question for the sector.