Information correct as of 28 May, 2026.

Focus on Taiwan

Market overview

The Taiwanese Government planned in 2017 to have an energy mix comprised of 50 per cent natural gas, 27 per cent coal, 20 per cent renewable energy, 2 per cent other energy and 1 per cent nuclear energy by 2025. However, according to the “2024 National Electricity Supply and Demand Report” released by the Ministry of Economic Affairs, the original goal of achieving a 20 per cent share of renewable energy by 2025 has been delayed and is now expected to be reached by November 2026, with an interim target of 30 per cent renewable energy by 2030.

With the exception of China, Taiwan is the largest offshore wind market in the Asia Pacific region and is developing rapidly. To meet the renewable energy target, the Taiwanese Government aims to increase installed offshore wind capacity to 5.3GW by the end of 2026 and reach approximately 13GW by 2030. But there are several factors which may delay buildout of these projects, including macroeconomic conditions, permitting and consenting processes, supply chain, infrastructure availability, localisation and uncertainty around financing.

Taiwan’s ambitious program to promote offshore wind power as a major energy source has continued to progress. As of 22 April 2026, Taiwan had installed approximately 4.6GW of offshore wind capacity. The MOEA expects installed offshore wind capacity to reach 5.3GW by the end of 2026.

The Ministry of Economic Affairs published new rules in August 2021 surrounding the development of the third phase of the offshore wind energy projects. Based on the foregoing, from 2026 to 2035, a capacity of 15GW is planned and the island aims to increase installed capacity by 1.5 GW each year. With intense competition among wind farm developers, bidders in rounds 3.1 and 3.2 bid their proposed power purchase agreement (PPA) feed-in-tariff price at NTD 0 /kWh or NTD 0.1/kWh to BOE (now known as the Ministry of Economic Affairs “MOEA”) to win the development rights. This makes offtake arrangements with corporate buyers via corporate power purchase agreements (“CPPA”) a critical requirement for project viability and bankability.  This trend towards CPPAs follows a similar global pattern towards net zero, which is in turn fueling local corporate buyers’ demand for green energy. This trend has been further supported in Taiwan by the Renewable Energy Development Act, which requires certain large electricity users in Taiwan to source 10 per cent of their energy needs from renewable sources.

The tender mechanism for round 3.3 was further refined in March of 2026, pursuant to which 3.6GW of capacity will be allocated for projects scheduled to be completed and connected to the grid in 2030–2031. Unlike in previous rounds 3.1 and 3.2, round 3.3 places greater emphasis on the bidding developer’s track record, financial capability and project execution capability, and introduces a floor  feed-in-tariff price of NTD 2.29/kWh, which aims to enhance the offtake structure for these projects while continuing to encourage CPPAs as the primary offtake mechanism.  Local content requirements have also been softened and replaced by a new ESG scoring criteria, although it remains to be seen in practice whether projects with greater local content will maintain a competitive advantage in scoring versus those that do not.

The Formosa 1 project was the first offshore demonstration wind farm in Taiwan. Completed in 2019, the total generation capacity of Formosa 1 is 128MW. The project is owned by Ørsted, JERA, Seagull and Stonepeak.

The Formosa 2 project was completed in 2023. The 376MW project is currently jointly developed by Synera Renewable Energy Group and JERA Nex bp.

The Greater Changhua 1 and 2a offshore wind project were completed in April 2024 after having achieved first power in April 2022. At 900MW, the project is Taiwan’s largest offshore wind project. The project is located 35-50 km off the coast of Changhua County. The 605 MW Greater Changhua 1 is owned by a consortium comprising Ørsted, Caisse de dépôt et placement du Québec (CDPQ) and the Taiwanese private equity fund, Cathay PE. The 295 MW Changhua 2a is owned solely by Ørsted.

Ørsted is also developing the 920MW Changhua 2b & 4 projects (which are expected to reach commercial operation in Q3 2026), the 570MW Greater Changhua 3, 3GW Wo Neng 1&2 and 2.1GW Xu Feng 1,2,3 projects.

In May 2024 the 600MW Changfang and Xidao projects off the coast of Taichung reached completion. Copenhagen Infrastructure Partners, which owns the majority of Changfang and Xidao projects, is also developing the 300MW Zhong Neng and 495MW Fengmiao projects. The Zhong Neng project reached commercial operation in May 2025, while the Fengmiao project is expected to be completed by the end of 2027.

By August 2025, Skyborn Renewables GmbH’s 640MW Yunlin offshore wind farm had begun commercial operation at its full design capacity, following completion of construction in December 2024 and full energization in January 2025.

Taiwan offshore wind projects

Project name MW Support/ Offtake Status Shareholders
1. Formosa 1 128 Program Demonstration project
Completed 2019; in operation
Ørsted, JERA, Seagull, Stonepeak
2. Changhua 109.2 Program Demonstration project
Completed 2021
Taiwan Power Company
3. Greater Changhua 1 605.2 Feed-in tariff Awarded Round 1
Completed 2024; in operation
Ørsted, CDPQ, Cathay Private Equity
4. Greater Changhua 2a 294.8 Feed-in tariff Awarded Round 1
Completed 2024
In operation
Ørsted
5. Hai Long 2a, 2b and 3 1,022 Feed-in tariff/CPPA Awarded Rounds 1 and 2
Construction
Northland Power, Mitsui, Gentari International Renewables
6. Yunlin 640 Feed-in tariff Awarded Round 1
Completed 2025
In operation
Skyborn Renewables, TotalEnergies, Electricity
Generating Public Company and Sojitz Corporation
7. Taoyuan 350 Awarded Round 1
License application rejected
WPD Taiwan Energy Co. Ltd.
8. Changfang - Xidao 595 Feed-in tariff Awarded Round 1
Completed 2024
Copenhagen Infrastructure Partners majority-owned through CI II and CI III; minority stakes held by GPSC, Taiwan Life and TransGlobe Life
9. Formosa 2 376 Feed-in tariff Awarded Round 1
Completed 2023
In operation
Synera Renewable Energy Group, JERA Nex bp
10. Changhua 2 294.5 Program Awarded Round 1
Construction
Taiwan Power Company
11. Hai Xia 1 300 Feed-in tariff Awarded Round 1
Development
LeaLea Group and Skyborn Renewables
12. Datian 165 Feed-in tariff Awarded Round 3.1
Withdrew
Skyborn Renewables
13. Greater Changhua 2b and 4 920 Program Awarded Round 2
Construction

Greater Changhua 2b: Ørsted

Greater Changhua 4: Ørsted, Cathay Life Insurance, Cathay Power Corporation, Cathay Wind Power Holdings

14. Zhong Neng 300 Feed-in tariff Awarded Round 1
Completed 2025
In operation
Copenhagen Infrastructure Partners and China Steel Corporation
15. Fengmiao 495 CPPA Awarded Round 3.1
Construction
Copenhagen Infrastructure Partners
16. Formosa 3 / Haiding 2 600 CPPA Awarded Round 3.1
EIA approved.
Corio Generation, TotalEnergies
17. Wei Lan Hai Changhua
(previously known as Huan Yang)
440 CPPA Awarded Round 3.1
Development
EIA approved
EDF Renewables and Taiya Renewable
18. Formosa 4/Haisheng 495 CPPA Awarded Round 3.1
Development
Synera Renewable Energy, Taiwan Petroleum
Corp, J&V Energy Technology Co, Yeong Guan
Group and Tien Li Offshore Wind Technology Co
19. Hai Xia 2 300 CPPA Awarded Round 3.1
EIA approved
LeaLea Group and Skyborn Renewables
20. Wo Neng 1, 2 1,000~1,500 Development Ørsted
21. Xu Feng 1, 2, 3 1,350~2,100 Development
EIA approved.(Xu Feng 2, 3)
Ørsted
22. Youde 700 CPPA Awarded Round 3.2
EIA approved
Shinfox
23. Formosa 6/Haiguang 800 CPPA Awarded Round 3.2
EIA approved
Synera Renewable Energy
24. Greater Changhua 3 570 CPPA Development Ørsted
25. Feng Miao 2 600 CPPA Awarded Round 3.2
Development
Copenhagen Infrastructure Partners
26. Formosa 3 / Haiding 1 360 CPPA Awarded Round 3.2
EIA approved
Corio Generation and TotalEnergies
27. Deshuai 240 CPPA Awarded Round 3.2
Development
Enervest
28. Hsinchu Winds of September
(floating)
Up to 1,000 Unknown Announced
EIA approved
BlueFloat Energy
29. Hai Shuo - Formosa 5
(floating)
Up to 1,536 Unknown Development
EIA approved
Synera Renewable Energy

Taiwan: Support regime and offtake

There are two principle support schemes for offshore wind:

Offshore Wind Power Demonstration Incentive Program (the “Program”)

The Program was introduced on July 3, 2012 in accordance with Paragraph 3 of Article 11 of the “Renewable Energy Development Act” to encourage the development of demonstration offshore wind farms by providing a Government subsidy for selected demonstration offshore wind projects. Under the Program, the installation of offshore demonstration wind turbines was to be completed by 2016, with the development of the demonstration wind farms to be completed by 2020. Three demonstration offshore wind farms were selected and supported by the Program; however, the projects actually completed under the Program were Formosa 1 and Taipower Phase I, with a total installed capacity of approximately 237MW. The Program provides a subsidy of up to 50 percent of the installation expenditure for the installation of demonstration wind turbines. During the operation phase, the Program provided incentive fees of up to NT$250m.

Feed-in-tariff (FiT)

The Renewable Energy Development Act provides the developer with a 20-year guaranteed PPA with Taipower at a contracted FiT rate. The FiT rate which may be granted is set by the MOEA and is reviewed annually. In practice, the MOEA would publish the FiT rate applicable to the PPAs executed in the relevant year. The 2020 FiT rate was 5.0946 (NT$)/kWh (roughly US$0.1691) (applicable to PPAs signed in 2020). The 2021 FiT rate was 4.6568 (NT$)/kWh (applicable to PPAs signed in 2021). The 2022 FiT rate was set currently at 4.5024 (NT$)/kWh (applicable to PPAs signed in 2022). The 2023 FiT rate was 4.5085 (NT$)/kWh (applicable to PPAs signed in 2023).~~~~

The offshore wind FiT rate remained at 4.5085 (NT$)/kWh in both 2024 and 2025. Options are also available to front-load the FiT rates during the first ten years or to back-load in the last ten years.

In comparison with FiT rates in Europe at the time, the Taiwanese FiT rates for earlier offshore wind projects were significantly higher, reflecting the relative inexperience of the market and supply chain. However, for later-stage offshore wind projects, particularly those successful under the third phase of Taiwan’s zonal development programme, the support and offtake structure has increasingly shifted from traditional FiT-based PPAs with Taipower to CPPAs with corporate buyers. In March 2026, the MOEA announced the selection mechanism for Round 3.3, under which CPPAs remain the primary route to market, but a floor purchase price of NT$2.29/kWh is introduced for surplus green electricity to support financing and reduce development risk.

Grid auctions

Taiwan expects to see offshore wind capacity increase by 15 GW between 2026 and 2035, with the expectation of installed capacity increasing by approximately 1.5 GW per year.

Grid connection capacity is auctioned by the MOEA. Whilst the first allocation round (April 2018) was awarded on the basis of FiT rates, the second allocation round (June 2018) was auction-driven and attracted seven participants for ten projects.

Taiwan's offshore wind Round 3.1 concluded on 30 August 2023 with a total awarded capacity of 2.335GW out of the 3GW available. The outcome of Round 3.1 reflected an increasingly severe market environment. This undersubscription, coupled with the subsequent withdrawal of certain developers, highlights the significant headwinds faced by the industry, including high financing costs and supply chain constraints. The transition to a "NT$0" bid era has increased pressure on project bankability, leading to a more cautious investment environment. The projects were originally scheduled for grid connection by 2026/7. The winning projects comprised:

Project name MW Ownership
Feng Miao 500 Copenhagen Infrastructure Partners
Formosa 3 - (Haiding 2) 600 CORIO / TotalEnergies
Hai Xia Phase 2 300 Skyborn
Formosa 4 495 SRE
Ocean (Huan-Yang) 440 EDFR/Taiya

In August 2024, the MOEA released the list of the projects awarded capacity in the latest offshore wind tender round (Round 3.2). Five offshore wind farms with a combined capacity of 2.7GW were awarded capacity The originally planned capacity limit for this phase was 3.6GW.

The five wind farms that were awarded development rights in Round 3.2 all submitted bids coming in at NT$0 per kWh. This pricing structure necessitates that the projects secure CPPA. The winning projects comprised:

Project name MW Ownership
Youde 700 Shinfox
Formosa 6 800 Synera Renewable Energy
Fengmiao 2 600 Copenhagen Infrastructure Partners
Formosa 3 / Haiding 1 360 Corio Generation and TotalEnergies
Deshuai 240 Enervest

Upon confirmation of their capacity allocations, developers must sign contracts within three months. The current offshore wind power plan targets grid connection between 2028 and 2030.

The tender mechanism has since been further adjusted. In March 2026, the MOEA announced the selection mechanism for Round 3.3, under which 3.6GW of capacity will be allocated for projects scheduled to be completed and connected to the grid in 2030–2031. Unlike the earlier price-bidding rounds, Round 3.3 introduced a floor purchase price of NT$2.29/kWh and removed mandatory local content requirements in favor of ESG-based incentives. Looking ahead, the MOEA expects to launch Round 3.4 in late 2026 or early 2027. In addition to the refinements to the evaluation criteria explored above, two other new incentive mechanisms have also been introduced.  The first is an up to 5 year electricity license extension for developers who can reach COD early and demonstrate promotion of energy resilience, local industry and economic development.  The second is a capacity extension mechanism, enabling successful developers the opportunity to expand their awarded capacity by up to 100% of their award vis-à-vis any unawarded sites.

Following the anticipated opening up of the "Taichung Direct Flight I-Point" and its navigation channel, approximately 4GW to 6GW of new capacity is expected to be released for development. This phase will also likely incorporate the 2.2GW of unallocated capacity from previous rounds, making it a critical final stage for fixed-bottom offshore wind projects.

Taiwan: Challenges

Marine spatial planning

In 2023 the Renewable Energy Development Act was reformed allowing offshore wind farm development beyond a 12 nautical mile zone. However, there is still a lack of a clear approval pathway and alignment with other marine users and their respective authorities in that area.  There is also an increasingly limited number of viable sites for future, fixed-bottom offshore wind development so further development areas will need to be identified and offered by the Government if the stated offshore wind ambitions are to be achieved.

Arbitrary fisheries compensation scheme

The “offshore wind power plant fisheries compensation formula”, applicable to fisheries affected by offshore wind power plants, has been described by some participants as arbitrary.

Fishery rights and fishing areas are poorly defined which has compounded the difficulties faced by developers seeking to engage with the local fishing industry.  While the challenges posed by this issue were most acute for the first projects developed, a number of projects have now managed to successfully overcome this obstacle and reach financial close and COD highlighting the increasing maturity of the development market in overcoming such issues.

Grid and port infrastructure

Port and vessel availability remains an ongoing challenge for projects in Taiwan as many Taiwanese ports are built as either commercial or fishing ports.  These constraints have principally been solved by collaborative efforts between developers and their supply chain, working together with port owners and operators to secure upgrades and capacity to enable projects to be developed.

Growing grid constraints will also require upgrades to accommodate new connections in remote areas.

Supply chain and local content

Historically, Taiwan has applied strict local content requirements as part of its project award criteria. Bidders in Taiwan’s 2022 tender needed to secure local content, including turbine components and underwater foundation services, for at least 60 per cent of the project’s capacity. This policy had clear implications on project delivery from a time and cost perspective. It also proved difficult to adhere to in practice, given the inherently global and specialized nature of the offshore wind supply chain. It also had flow on consequences on vessel availability as well as on other ancillary parts of the supply chain.

In July 2024, the EU accused Taiwan's local content requirements of violating competition principles and filed a consultation request with the WTO. In response, the MOEA stated that the direction of communication during consultations is moving toward "lifting localization restrictions and the local content requirements will be removed in Round 3.3". For Round 3.3, the MOEA has indeed removed mandatory local content requirements; however, those express local content requirements have been replaced by a new selection mechanism that includes “local industrial and economic benefits” as part of the ESG planning criteria under the project execution capability assessment and also provides incentives for projects willing to create local industrial and economic benefits.  It remains to be seen whether this policy shift will be used to impose local content requirements under another guise.

Alternate offtake structures

Under the latest auction mechanism for the third selection round of Taiwan’s offshore wind zonal development programme announced in March 2026, CPPAs remain the primary route to market for generators. However, the mechanism now introduces a floor purchase price for surplus green electricity of NT$2.29/kWh, based on Taipower’s average avoided cost, to support project financing and reduce development risk. This represents a shift from the earlier Round 3.2 tender, where bids came in at NT$0 per kWh and developers were required to secure their own revenue streams primarily through CPPAs. Direct wire PPAs, retail / sleeved PPAs and virtual PPAs are permitted in Taiwan. Taiwan’s CPPA market continues to be supported by corporate buyers’ demand for renewable electricity.

We have also seen the emergence of new entities and structures to support the growing demand for long-term CPPAs. This includes the formation of Taiwan Smart Electricity & Energy Co. Ltd. (TSEE), a Taiwan-based wholesale power distribution company that will initially specialize in offshore wind power.  TSEE will act as a demand aggregator, effectively sitting between the offshore wind farm power generator and a collection of ultimate consumers.  TSEE therefore plays both a credit enhancement and demand aggregation role, helping to match corporate power demand with the long-term, credit supported bankability requirements of offshore wind projects.

Construction delays and supply chain challenges

Some projects have experienced issues during construction – including cost overruns – in recent years which has caused concerns in the finance market.  Factors that have contributed to delays have included:

  • Inflation and associated increases in finance costs.
  • Supply chain issues.
  • Geopolitical instability, which has precipitated increased commodity prices, including oil and steel, and increased foreign exchange costs.
  • Increased demand and limited supply of suitable specialised vessels and essential plant and equipment needed for the construction of the turbines.
  • Worse than anticipated weather conditions during construction windows.
  • Suboptimal ground conditions, resulting in technical re-evaluations of the planned monopile and jacket structures.
  • Increasing technical complexity as projects move into deeper waters.

Credit guarantee scheme and finance market conditions

The MOEA has launched a power credit guarantee scheme to mitigate the counterparty risk of offshore wind projects contracted under CPPAs to facilitate their project financing. The credit guarantee is available to renewable CPPA customers that consume more than 500,000 MWh of power a year or possess a credit rating that meets a specified threshold. Under the scheme, CPPA customers pay insurance premiums to government-owned banks in exchange for performance guarantees of up to 20 years. These banks obtain reinsurance through the National Credit Guarantee Administration (NCGA), which is backed by the Export and Import Bank of The Republic of China (EximBank).

In February 2025, the MOEA further stated that the national credit guarantee mechanism would support offshore wind financing and green electricity procurement, with estimated offshore wind financing demand of NT$1.08 trillion between 2026 and 2031, total guarantee capacity of NT$90 billion, and the guarantee ratio for green energy construction projects increased from 60 per cent to 80 per cent. The availability of broader NCGA support has improved liquidity for financings, particularly from local Taiwanese lenders.  The Taiwanese offshore wind finance market continues to be dominated by a combination of international commercial lenders and ECAs, with Taiwanese lenders playing an increasing role in providing liquidity to greenfield as well as brownfield offshore wind projects pursuing refinancing strategies. Catalysing Taiwanese bank finance for offshore wind remains critical to enabling international commercial lenders and ECAs to recycle capital towards greenfield assets where their global offshore wind expertise is most useful.  It also serves as a useful mitigant against volatile FX and other finance related costs, given the competitiveness of their NTD cost of funding.

Floating offshore wind

With the availability of suitable sites for fixed bottom offshore wind diminishing, the prospect of floating offshore wind farms being developed in Taiwan is increasing, with certain developers having recently announced their ambitions in this respect. In addition to the usual areas of focus, floating offshore wind will invite increased scrutiny regarding mooring risks, inter array cable flexibility and the overall O&M strategy (including vessel availability throughout the operational period). It will also be important to ensure that the relevant supply and installation contracts are clear on the mitigation measures required of each contractor as well as the compensation mechanics available to the project should risks associated with each of those specific packages materialise. See our article about floating offshore wind here.

Country overview

  • content-type:insights/publication
  • nrf-migrated:article-categories/international-offshore-wind/international-offshore-wind