The landscape on expanding the UK Emissions Trading Scheme (UK ETS) to include waste incineration and energy-from-waste (EfW) facilities has evolved over recent years. There was a consultation published in May 2024, an interim consultation response issued in July 2025, and a series of additional policy developments, including a new voluntary monitoring, reporting and verification (MRV) period which commenced on 1 January 2026. In this update, we consider the key developments, the issues that remain unresolved, and what EfW operators and their customers need to be considering.
Recap of UK ETS and voluntary MRV period
In May 2024, the Department for Energy Security and Net Zero (DESNZ) published a consultation on expanding the UK ETS to include EfW and waste incineration facilities, building upon the UK ETS Authority's July 2023 response which had set out the broad parameters of the expansion. The 2024 consultation proposed that the UK ETS would apply to facilities conducting incineration and combustion of waste, as well as other forms of energy recovery from waste including fuel production. Our article providing a general summary of the July 2023 Response can be found here.
On 21 July 2025, the UK ETS Authority published its interim response to the 2024 consultation. The interim response addressed details of the MRV framework for the forthcoming monitoring period, deferring all final policy decisions – including how ETS costs will work and the full impact on local authorities – to a second response which has not yet been scheduled. Details of the interim response included:
- Voluntary MRV period: The UK ETS Authority confirmed that a voluntary MRV-only period would commence on 1 January 2026. Under this period, operators are encouraged to measure, report and verify their emissions and share this data with their regulators to support the finalisation of policy decisions, including cost-pass through and MRV methodologies. There will be no penalty for not participating in the MRV period. The MRV-only period will apply to combustion and process emissions from incineration and EfW processes, including from non-mechanical or chemical recycling processes and, provisionally, from Persistent Organic Pollutants (POPs) incinerators and clinical waste incinerators. If operators decide to participate in the MRV-only period, operators will need to report emissions to the relevant regulator for their facility: the Environment Agency; the Scottish Environment Protection Agency; Natural Resource Wales; the Department of Agriculture, Environment and Rural Affairs, Northern Ireland; or DESNZ.
- Scope threshold: Any facility above the capacity threshold of a small waste incineration plant – facilities burning non-hazardous waste of more than three tonnes per hours or hazardous waste exceeding 10 tonnes per day – will be in scope of the MRV period.
- Monitoring methodology: The UK ETS Authority adopted an integrated monitoring approach combining three methodologies: direct CO2 monitoring via Continuous Emissions Monitoring Systems (CEMS); carbon-14 analysis to differentiate fossil and biogenic CO2; and emissions factors based on waste type and composition. Larger facilities emitting more than 50,000 tonnes of CO2 annually are expected to use CEMS and carbon-14 equipment unless they can demonstrate this is technically unfeasible or disproportionately costly. Smaller facilities opting in to the voluntary MPV period may apply to use emissions factors instead.
- No commitment on the 2028 implementation date: Most significantly, the interim response made no commitment on when EfW will be formally included in the UK ETS. The UK ETS Authority stated that it will consider the findings and data collected during the voluntary MRV period before confirming the plans and details for full inclusion.
In December 2025, the UK ETS Authority announced that the ETS will run for a second phase from 2031 to 2040 and remain consistent with long-term decarbonisation goals, providing the long-term investment signal required for heavy infrastructure projects such as carbon capture and storage (CCS).
Key challenges arising from expansion of the UK ETS to the EfW sector
- Cost pass-through and local authority exposure to costs of EfW compliance with ETS: EfW compliance with ETS may be costly. The continuous emissions monitoring systems (CEMS) equipment required to monitor emissions under the voluntary MRV scheme can cost up to £1 million. Other factors contributing to the monitoring cost include sampling and testing, as operators will need to ascertain the carbon content of waste to understand their potential liability. EfW companies are the regulated parties at the point of obligation, and will be expected to shoulder not only the cost of purchasing and surrendering allowances in the first instance, but also the cost of monitoring, sampling and testing. In practice, however, these costs are likely to be passed through to consumers and local authorities. A related concern is that the regulatory mechanism addressing cost pass-through has not been finalised since the July 2025 interim response, and there is a risk that the scheme acts as an additional cost of waste disposal that falls to local authorities. In our article from August 2023, we flagged issues on cost allocation and renegotiating contracts. Although operators will pick up these costs in the first instance, parties will need to negotiate the allocation of costs in the long run.
- Waste diversion from EfW facilities: If the cost of ETS compliance for EfWs rises above the cost of sending waste to landfill, operators and local authorities may be incentivised to divert waste away from EfW facilities. The simultaneous increase in landfill tax this year may act as a deterrent, but the balance will need to be carefully maintained. Similarly, if the cost of ETS compliance rises above the cost of sending waste to European energy recovery facilities, there may be an incentive to divert waste outside the UK to European EfW facilities that are not subject to equivalent carbon pricing obligations, undermining the domestic EfW market and exporting the associated carbon emissions.
- Linkage to EU ETS: The question of whether the EU ETS will be expanded to cover EfW facilities continues to be relevant to the UK position. The European Commission was required to study the feasibility of including EfW and waste incineration in the EU ETS and to report back by July 2026. If the EU proceeds with inclusion, it is tentatively considering a 2030 implementation date under an opt-out clause. Meanwhile, in May 2025 it was announced that the UK and EU ETS are to be linked. This development may have a considerable impact for the EfW sector, as any linkage is likely to require the UK to align with EU rules on which sectors are required to purchase carbon allowances.
On the horizon
Voluntary MRV: The voluntary MRV period is now underway, and operators who have not yet submitted a voluntary monitoring plan application are encouraged to do so as a matter of priority. The MRV will be used as a trial period for the government to inform further policy developments particularly in relation to links between MRV and ETS cost pass-through.
The government’s second response is expected to set out final policy decisions, include details on cost pass-through mechanisms and address impacts on local authorities. There is no set timeline for when this is to be published. This response will be the critical document for EfW operators and their customers as it should confirm (or revise) the 2028 implementation date and provide regulatory certainty surrounding cost pass-through.
European Commission’s report on EU ETS EfW inclusion: The European Commission is expected to publish its feasibility study on EU ETS EfW inclusion in July 2026, which will be a further important data point. As discussed earlier, the European Commission is considering including EfW in the EU ETS from 2028 onwards, with a possible opt-out until 31 December 2030.1 The report is expected to expand on the grounds of the 2030 opt-out, whether the EU ETS obligation will apply only to fossil emissions (and not biogenic materials), which greenhouse gases will be covered, monitoring requirements and applicable ETS requirements for EfWs based on size. Formal negotiations to link EU and UK ETS between the European Commission and the UK began in January 2026.
CCS consultation: The UK ETS Authority published a consultation on the regulation of cross-boundary CCS pipelines. The consultation is open until 4 June 2026 and seeks input on how to streamline the regulatory framework governing CCS pipelines that cross jurisdictional boundaries within the UK. Under the current framework, operators of CCS pipelines that cross the territories of more than one of the four countries, or that transition from land into UK waters and beyond, are required to obtain a separate UK ETS permit from each relevant regulator and install monitoring infrastructure at each regulatory boundary. The Authority considers this arrangement to be unnecessarily complex and risks inhibiting the commercial viability of CCS as a solution to managing emissions from EfWs.
The consultation proposes to reduce the maximum number of regulators a pipeline operator is required to engage with when transporting captured CO2 offshore and seeks views on appropriate locations for monitoring infrastructure where regulatory responsibility passes from onshore to offshore regulators. This directly addresses industry issues, such as the prohibitive cost of CCS for EfW operators not situated near CCS clusters. CCS has already been recognised as a potential solution, particularly with Encyclis’s plans for its Protos EfW to develop a carbon capture facility to transport captured CO2 to the Hynet Cluster in Liverpool Bay via pipeline. The Encyclis carbon capture plant is expected to become operational in 2029.
Next steps
With the voluntary MRV period now underway, the ETS expansion to EfW is gaining momentum but significant uncertainty remains. Stakeholders should watch closely whether the government’s second response to their interim response addresses the unique position of EfW operators as providers of essential waste management functions which do not control the fossil carbon content of the waste they receive, and whether this warrants any mitigation in recognition.
Following the close of the consultation on cross-boundary CCS pipeline regulations in June 2026, it will also be important to assess whether regulatory simplification translates into increased CCS investment for EfW facilities, or whether geographic and economic barriers continue to limit the CCS pipeline pathway to a small number of well-connected operators.
Looking further ahead, the key question will be whether any opt-out mechanisms surface in the context of the UK-EU ETS linkage, though operators should not lose sight of the longer-term picture. It is the UK ETS Phase II framework for 2031 to 2040 that will ultimately set the carbon price and allowance trajectory that determines whether the ETS genuinely drives the transformation of the EfW sector.
We would like to thank Madeline Lee for their contribution to this article.