The Leaseholder Remediation (Building Safety) Bill (the "Bill") was introduced in the House of Lords as a Private Members' Bill on 9 June 2026, sponsored by Baroness Pinnock, and is intended to build upon and extend the policy intentions and objectives of the Building Safety Act 2022 ("BSA 2022").
Whilst the BSA 2022 includes important leaseholder protections through Part 5 and Schedule 8, those protections are subject to notable limitations: they apply only to “relevant buildings” of at least 11 metres in height or five storeys; they impose caps (depending on property value) rather than complete prohibitions for non-cladding defects; and leaseholder eligibility requires meeting a test for “qualifying leases.”
The Bill seeks to address these perceived gaps with a view to the government enacting further legislation. Despite being a Private Members Bill (so not guaranteed parliamentary time and indeed it may not even progress to a second reading) the policy objective is clear: to ensure that no leaseholder bears the financial burden of historical building safety failures, regardless of the size or height of their building. Below we summarise what the impact would be if the Bill becomes law.
Main provisions
Prohibition on Passing Remediation Costs to Leaseholders (Part 1)
The centrepiece of the Bill is an absolute prohibition on passing remediation costs to protected leaseholders. Clause 1 provides that no remediation cost in respect of a “systemic defect” may be passed to a protected leaseholder by service charge or otherwise. Any lease or contract term purporting to render a leaseholder liable for such costs would be void to that extent.
- Definition of “relevant building” - crucially, the definition of “relevant building” encompasses any residential building containing one or more leasehold properties. There is no minimum height or storey threshold, a significant departure from the BSA 2022.
- “Systemic defects” - the defects included within the prohibited remediation costs are not limited to cladding. Clause 3 defines “systemic defects” more broadly to include structural defects, unsafe cladding, deficient or missing fire-stopping systems, compartmentation, insulation, fire detection systems, and any other system or component determined by a competent person to present a building safety risk. Notably, the burden of proof that a defect does not fall within these categories lies on the building owner, not on the leaseholder. This is another shift from the current regime (which requires leaseholders to prove that something is a relevant defect).
- Protected leaseholders - a “protected leaseholder” is defined under clause 4 as any leaseholder holding a lease of a dwelling in a relevant building, unless they are (or were at any material time) the developer. The BSA 2022’s requirements for a long lease, residency, or a cap on the number of properties owned are removed entirely. Protection applies to current and subsequent holders of the lease.
Clause 5 renders void any service charge demand requiring contribution to remediation costs and provides that leaseholders who have paid such charges on or after 14 February 2022 may apply to the First-tier Tribunal (Property Chamber) for a repayment order, subject to a six-year limitation period.
Liability and Recovery (Part 2)
Clause 6 identifies “responsible persons” who bear primary liability jointly and severally as:
- the developer;
- the building owner at the time relevant works were carried out;
- any contractor who carried out the defective works; and
- any manufacturer or supplier of defective components or materials.
The current building owner is also liable unless they can demonstrate both that they had no knowledge of the defect at acquisition and that they have taken all reasonable steps to identify and pursue the responsible persons.
The Building Safety Regulator ("BSR") has enforcement powers under clause 7, including the ability to investigate breaches, issue remediation notices, apply to the High Court for injunctions, and prosecute offences.
Remediation Obligations and Timeframes (Part 3)
- Enforceable remediation timeframes - clause 8 empowers the BSR to serve remediation notices requiring responsible persons to carry out specified works and to provide a remediation programme within 28 days. Clause 17 imposes mandatory completion deadlines: six months for interim or emergency safety works, and 24 months for all other relevant works (from the date of the BSR’s remediation notice).
- Remediation Acceleration Plan - the Secretary of State is required under clause 10 to publish a Remediation Acceleration Plan within 6 months of the Act being passed, setting out the number of affected buildings, target completion dates, resourcing measures, and reporting mechanisms. This must be updated annually.
- Non-compliant developer consequences - clause 11 provides a significant enforcement mechanism: developers subject to unremedied remediation notices are prohibited from obtaining planning permission or building control approval for new major residential development until they are compliant.
Recoupment, Licensing, and Developer Accountability (Part 4)
- Developer claims for remediation costs - the Bill enables developers who have incurred remediation costs to bring claims against manufacturers and suppliers of defective products in the High Court, within a six-year limitation period from when the remediation costs were incurred.
- Licensing regime - clause 13 requires the Secretary of State to establish a licensing regime for developers of large residential buildings (i.e. a building at least 11 metres in height or at least five storeys). Operating without a licence is a criminal offence, and the BSR may refuse or revoke licences for non-compliance. In addition, the BSR will publish and maintain a register of developers holding a licence.
Leaseholder Rights and Remedies (Part 5)
- Right to remediation information - leaseholders may serve notice on the building owner requiring disclosure of fire safety assessments, BSR correspondence, warranty documentation, identity of responsible persons, and remediation timetables within 28 days. Non-compliance is a criminal offence.
- Individual remediation claims - leaseholders who have suffered loss may bring claims in the county court or First-tier Tribunal. Recoverable losses include increased insurance premiums, interim protection costs (e.g. waking watch), mortgage costs, and diminution in dwelling value. The limitation period does not run until the leaseholder knew or ought to have known of the defect and the responsible person’s identity.
- Leaseholder Remediation Ombudsman - the Secretary of State must appoint an independent ombudsman within 12 months to investigate complaints about unremediated defects or contraventions of the Act.
- Remediation work timeframe – the Bill imposes timescales within which remediation works must be completed – six months for emergency safety works, and 24 months for all other works, beginning on the date on which the BSR issued a remediation notice.
Impact on the Real Estate Sector
- Building owners and freeholders - the Bill represents a fundamental shift in the allocation of remediation costs. Building owners will need to conduct urgent assessments of all residential buildings (regardless of height) to identify potential systemic defects. The removal of the height threshold means that portfolios previously considered outside the scope of the BSA 2022 are now squarely within scope. Prospective building owners will also need to review their acquisition due diligence practices and ensure that any defects are identified and disclosed early.
- Property agents and managing agents - managing agents will need to review all service charge budgets and demands to ensure that no remediation costs are being passed to protected leaseholders. Existing demands may need to be withdrawn. Agents will need to establish clear protocols for responding to leaseholder information requests, noting that failure to comply within 28 days is a criminal offence. Agents advising on transactions will need to address the expanded scope of leaseholder protections in pre-contract enquiries and certificates of compliance.
- Developers and manufacturers - developers face the dual threat of direct remediation liability and the prohibition on obtaining planning permission for new developments whilst subject to unremedied notices. The licensing regime introduces a further compliance obligation. Manufacturers and suppliers of building products should be aware of the recoupment mechanism which exposes them to claims from developers who have remediated defects attributable to defective products.
What next?
The Bill is still very much in its infancy and, with such bold suggested changes and wide-reaching ramifications (with the potential to create huge upheaval), it is unlikely that it will progress in its current form and may not even reach a second reading. If it does progress, it would represent the most significant expansion of leaseholder protections since the BSA 2022.
If the Bill becomes law, the practical implications for the real estate and construction sectors would be considerable. Building owners and managing agents would need to review their entire portfolios, service charge arrangements, and compliance procedures, and prepare for more structured information requests and potential claims.
Whether or not the Bill achieves Royal Assent, the direction of travel is clearly towards comprehensive leaseholder protection and strict accountability and liability for those responsible for building safety failures.