Across Europe, the rapid expansion of Al-driven data centre capacity is colliding with legacy electricity infrastructure that was never designed to accommodate loads of this scale or pace of delivery.
Grid connection queues now stretch up to 13 years in some of the continent’s most established digital hubs, and the traditional markets - Frankfurt, London, Amsterdam, Paris and Dublin - are increasingly congested. Demand is immense: European data centres consumed an estimated 96TWh of electricity in 2024, yet capacity is forecast to roughly double by the end of the decade.
The challenge is no longer whether demand exists, but whether reliable power can be delivered at the right scale, in the right location, and within an investable timeframe. As governments and regulators respond - from the EU Grids Package to national-level queue reforms - the relationship between grid access and project viability has become one of the defining issues for sponsors, lenders and advisers across the sector.
EU regulatory developments
The growing tension between rapidly increasing data centre electricity demand and limited grid capacity has placed grid access at the centre of the European policy agenda. The European Commission has increasingly focused on measures aimed at improving access to grid capacity and accelerating grid expansion.
A key development is the European Grids Package, published in December 2025, which seeks to address growing connection queues and grid congestion. In particular, the Commission encourages grid operators to prioritise connection requests based on project maturity and grid readiness, rather than relying solely on a first come, first served approach. While intended to ensure a more efficient allocation of scarce grid capacity, this may require data centre developers to secure permits, financing and project commitments at an earlier stage in the development process.
In parallel, the proposed Cloud and Al Development Act recognises the strategic importance of data centres for Europe’s digital economy. The proposal would require member states to establish dedicated acceleration zones for data centres, assess their future electricity needs and facilitate anticipatory grid investments. Together with streamlined connection procedures, flexible connection arrangements and support for PPAs, these measures are intended to improve power availability and provide greater certainty for future data centre projects.
Great Britain
In mainland GB, grid connectivity has become one of the key constraints on data centre development, alongside planning and consenting challenges. Between November 2024 and June 2025, contracted demand in the connections queue surged from 41GW to 125GW, with data centres alone accounting for around 73GW, equivalent to roughly one and a half times GB’s peak electricity demand.
As of July 2026, around 300 data centre projects were waiting for a grid connection. Many of these applications are considered speculative, with developers securing queue positions as a low-cost hedge against future demand rather than a firm commitment to build. The result is a distorted pipeline that delays viable projects and obscures signals for network investment and reinforcement.
The UK government and its regulators have responded with one of Europe’s most comprehensive grid connection reforms. The starting point was NESO’s Connections Reform Package (TMO4+), approved by Ofgem in April 2025, which replaced the legacy first come, first served model with a more selective “first ready, first connected” process. Under the new framework, generation and storage projects must demonstrate both readiness and strategic need, while demand projects - including data centres - are assessed primarily by readiness, reflecting the government’s growth and decarbonisation objectives. The reforms have removed hundreds of gigawatts of speculative projects from the queue and are expected to accelerate investment in both energy and digital infrastructure.
The next phase of reform has focused on large demand users, including data centres. Through its demand connections reform programme, Ofgem is considering a combination of commitment fees and enhanced queue management measures designed to ensure that developers demonstrate the financial capability and commercial maturity required to progress their projects. At the same time, the UK government is exploring mechanisms to accelerate the connection of strategically important demand projects, including through alternative and phased connection agreements, voluntary flexibility services, and self-build options for high-voltage assets.
While these reforms are likely to improve the connections process, they will not on their own close the gap between rapidly growing data centre demand and the pace at which the grid can be expanded. As a result, developers are increasingly targeting regions with available grid capacity rather than focusing exclusively on established data centre hubs. At the same time, developers are pursuing solutions that sit outside the traditional grid connection pathway. Co-location with generation assets - whether at former power station sites, energy parks or industrial clusters - offers a route to faster energisation by leveraging existing infrastructure.
Private-wire arrangements and behind-the-meter generation, typically gas-fired, with a transition pathway to cleaner technologies, are gaining traction, allowing operators to bring capacity online while awaiting permanent grid access.
Hybrid models - combining grid import with on-site generation, battery storage, renewable PPAs and demand-side flexibility - are also emerging as the pragmatic answer for data centre campuses that need to phase capacity over several years. While the regulatory and sustainability considerations of these structures are complex, they represent a growing and necessary part of the UK’s data centre delivery strategy, and for many projects, the difference between delivery and delay.
Moreover, they can help address broader offtake and power procurement challenges, including power price volatility, security of supply requirements and increasingly demanding sustainability objectives.
Netherlands
Like the UK, the Netherlands has been grappling with severe electricity grid congestion for several years. Connection queues continue to grow: According to the latest available figures for 2025, regional grid operators have 15,014 applications for consumption capacity on their waiting lists, representing more than 9.3GW of demand. At transmission level, 210 applications for demand connections, 35GW, and 168 applications for generation connections, 27.6GW, are awaiting capacity on TenneT’s grid. For data centres, whose business models depend on access to large and reliable electricity supplies, securing grid capacity has therefore become a critical factor in determining whether and when projects can proceed.
In practice, obtaining a new grid connection increasingly requires data centre developers to invest in energy infrastructure that falls well outside their traditional core business. Developers are often expected to contribute to solutions that help alleviate grid congestion and support the local grid operator. Examples include the deployment of battery storage systems, heat systems, or the development of privately financed and operated grids and substations.
Flexible assets such as battery storage are particularly valuable in this regard. Through contractual arrangements with the relevant grid operator, these systems can be made available to support the grid during periods of congestion. For data centres, such investments are no longer merely an optimization tool but are rapidly becoming an important, and in some cases essential, component of securing or expanding grid access for data centre projects.
The challenges do not end once grid capacity has been secured. For existing data centres, retaining contracted capacity is no longer guaranteed. Dutch energy regulator, the Authority for Consumers and Markets, has introduced several measures aimed at ensuring that
scarce grid capacity is used efficiently and does not remain unnecessarily reserved.
One important example is the Dutch “use-it-or-lose-it” regime. Under this framework, contracted grid capacity that remains unused for a prolonged period, typically around two years, may be withdrawn by the relevant grid operator. This is particularly relevant for data centre developments that have secured capacity during the development phase but have not yet commenced construction. Developers must be able to demonstrate tangible progress towards project realisation, such as obtaining permits, entering into construction contracts or otherwise advancing the project.
Another significant development is the mandatory contribution to congestion management. Large electricity users with contracted capacity exceeding 50MW are required to participate in congestion management schemes and to offer flexibility to the grid operator. This may take the form of capacity service contracts, which provide day-ahead flexibility, or redispatch agreements, which provide intraday flexibility. In practice, this often means reducing electricity consumption when requested by the grid operator during periods of congestion. The obligation may also be extended to smaller users in areas where voluntary flexibility arrangements prove insufficient.
Data centre operators should also keep an eye on a further regulatory development. In May 2026, a proposed code amendment was submitted to the Dutch regulator that would introduce additional connection requirements for power electronics-connected demand facilities of 10MW or more, including many large-scale data centres. If adopted, the new rules would impose additional technical requirements relating to matters such as frequency response, voltage control and the way in which facilities adjust their electricity consumption. The proposal would add a further layer of regulatory and technical compliance for new data centre developments.
The broader trend in the Netherlands is clear: obtaining and retaining grid capacity is no longer a given. Increasingly, data centre operators are expected to show that their facilities can operate in a way that supports the stability and efficient functioning of the
wider electricity system.
Snapshots
Germany
Europe’s largest economy and a major data centre market, but available grid capacity has become the sector’s new gold. A key challenge is the growing mismatch between renewable generation in northern Germany and historically major demand centres further south, especially in the Frankfurt region. While extensive grid expansion is underway, connection prospects increasingly depend on available capacity across multiple grid levels. Data centres also compete for scarce capacity with battery storage, electrolysers and other large loads, making sites with secured power access, or powered land, increasingly valuable.
The legal challenge therefore extends beyond obtaining a connection offer. Developers must determine how a data centre can be embedded in a wider infrastructure development combining renewable generation, battery storage, backup generation, heat offtake and, potentially, private-wire arrangements. Each interface raises distinct questions around grid connection rights, electricity supply, permitting, asset ownership and the allocation of curtailment and delay risk.
Germany’s Energy Efficiency Act adds further constraints, including efficiency, renewable electricity and waste-heat requirements. In practice, however, waste-heat utilisation depends on aligning data centres with heat-network infrastructure and commercially viable long-term offtake arrangements.
Italy
The country has seen rapid growth in data centre demand, but access to power and grid connectivity remain the central challenges. Connection requests to Terna, the national transmission system operator, significantly exceed available grid capacity, particularly in northern Italy, where grid capacity is most constrained. As a result, access to grid capacity has become a key factor in determining project timing and feasibility.
The regulatory landscape has evolved considerably in 2026. Article 8 of Decree-Law No. 21/2026, converted into Law No. 49/2026, introduced a unified authorisation procedure for data centres, bringing the principal permitting and connection-related approvals within a single framework and reducing the risk of delays caused by fragmented administrative processes.
At the regional level, Lombardy adopted Law No 11/2026, the first Italian legislation specifically dedicated to data centres. The law encourages development on brownfield sites located near existing grid infrastructure, provides incentives for projects meeting sustainability criteria and introduces phased approvals for projects above 50MW linked to infrastructure availability.
Together, these reforms reflect a broader shift in the Italian market. While permitting remains important, access to electricity is increasingly the main constraint. Developers are therefore focusing on sites with available grid capacity from the outset, making grid availability and energy strategy central considerations in project planning, financing and execution.
France
A rapid expansion of data centre capacity is raising a number of structural challenges relating to power procurement and grid connectivity. In France, the regulatory framework applicable to data centres has been shaped by the transposition of European Union directives, resulting in a series of legislative developments, notably through the DDADUE Act (Law No. 2025-391), and the SVE Act (Law No. 2026-403). These reforms have introduced a legal definition of data centres and established a regulatory framework addressing grid connection and environmental requirements.
The reconciliation of these objectives has been reflected in the creation of a special regulatory status for large-scale data centres contributing to ecological transition or national sovereignty. Such facilities may be designated as projects of major national interest, or PINMs. PINM designation entails certain regulatory and environmental derogations applicable to the transmission network connection infrastructure required for such projects. These measures notably include the power granted to the regional government to reprioritise projects within the public electricity transmission network connection queue where network congestion results in connection delays exceeding five years.
From an energy supply perspective, the French authorities also seek to ensure the environmental acceptability of data centre projects by imposing specific performance requirements. In that respect, data centres with an installed electrical capacity exceeding 1IMW are required to recover and utilise waste heat. In the event of non-compliance with this obligation, the French Ministry of Energy may order the data centre to implement the necessary corrective measures and may impose proportionate financial penalties.
This was first published in Project Finance International on 6 October 2026.