On 23 February 2026, the Environment Agency published its summary of responses and outcome to the consultation on Standard Rules Permit No. 32, which addresses how decarbonisation readiness (DR) requirements will be incorporated into standard rules environmental permits.

The outcome confirms the government’s intention to embed DR obligations firmly within the environmental permitting regime from 28 February 2026, with implications for operators of new and substantially refurbished electricity generating combustion plant.

What is decarbonisation readiness?

DR is the updated framework that replaces the former carbon capture readiness (CCR) regime. It was introduced through the Environmental Permitting (Electricity Generating Stations) (Amendment) Regulations 2025, which added new requirements to the Environmental Permitting (England and Wales) Regulations 2016.

From 28 February 2026, operators of the relevant plants must submit a report that demonstrates the installation has been designed so that, within its operational lifetime, it could be:

  • converted to hydrogen firing; or
  • retrofitted with carbon capture technology.

Key outcomes of the consultation

The consultation on Standard Rule Permit No. 32 sought views on how these new DR obligations should be reflected in standard rules permits, which are available for facilities considered to present a lower environmental risk.

The EA reported broad support for the incorporation of DR requirements into standard rules permits, with the consultation attracting responses from operators, industry bodies, regulators and other stakeholders with an interest in decarbonisation.

The outcome of the consultation confirms that operators will be required to:

  • prepare maintain a site-specific DR report;
  • keep that report under review and update it periodically over the life of the plant; and
  • provide the report to the Environment Agency (EA) on request.

Anaerobic digestion and carbon capture

Although anaerobic digestion (AD) facilities are not subject to the new statutory DR requirements, the consultation outcome confirms that the EA intends to pursue future amendments to certain AD standard rules permits.

The purpose of these changes would be to allow operators, where specific conditions are met, to undertake carbon capture, upgrading to biomethane and temporary storage of captured carbon dioxide for utilisation under standard rules, rather than requiring a bespoke permit.

Respondents broadly supported this approach as a means of reducing regulatory burden while maintaining environmental protections. Importantly, these proposals do not impose new mandatory obligations on AD operators at this stage; instead, they signal an intention to expand the scope of standard rules in the future to accommodate carbon capture activities where appropriate.

Withdrawal of SR2009 No. 4

Consistent with the consultation proposals, the EA intends to withdraw Standard Rules SR2009 No. 4 (combustion of biogas in engines at a sewage treatment works). The regulator considers that this standard rule is no longer being used, given changes in the regulatory landscape.

Why does this matter for operators?

The publication of the consultation outcome provides greater certainty on how DR will operate in practice under the environmental permitting regime. For operators, this marks a further step in the UK’s transition towards integrating net zero objectives into core environmental regulation.

In particular, affected operators should be aware that:

  • DR obligations will apply to permit applications submitted on or after 28 February 2026;
  • DR is no longer a one‑off assessment at the planning stage, but an ongoing operational consideration; and
  • standard rules permits will increasingly include forward‑looking design and review obligations linked to future decarbonisation pathways.

These requirements may have implications not only for permitting strategy, but also for project design, financing, and long‑term asset value.

Next steps

The EA will now update and finalise the relevant standard rules permit conditions and supporting internal and external guidance to reflect the consultation outcome.

Contact