To incentivise development of gas-fired power projects, Decree 56/2025/ND-CP (Decree 56) came into effect in Vietnam on March 3, 2025. Among other things, Decree 56 sets out the principles of minimum long term contracted electricity output for gas-fired thermal power projects using imported LNG.
Decree 56 currently provides that for a gas-fired thermal power project using imported LNG:
- The minimum long-term contracted electricity output shall not be lower than 65 percent of the “average electricity output over many years of the gas-fired power plant project”. The “average electricity output over many years” would be stipulated in the power purchase agreement determined in accordance with (x) the regulations on methods for determining electricity generation service prices; (y) principles for calculating electricity prices to implement electricity projects; and (z) main contents of the power purchase agreement issued by the MOIT.
- The minimum long-term contracted electricity output would only apply during the loan repayment period, capped at 10 years from the commercial operation date of the project (which as per Decree 56 is required to be prior to January 1, 2031), and the project completion needs to be accepted by the competent state agency prior to such date.
The above 10 year structure meant it would be difficult for banks to size debt beyond 10 years without assuming merchant risk or renegotiation risk. It would also cause a misalignment with the long-term (c.15-20 years) and take-or-pay nature of LNG sale and purchase agreements and obligations to offtake fixed annual contract quantities of LNG.
To overcome this and other potential bankability issues, a draft amendment to Decree 56 has been proposed by the MOIT to the Vietnam government on January 26, 2026 following feedback from developers and financiers.
If enacted, the minimum long term contracted electricity output would be increased from 65 percent to 75 percent of the multi year average electricity generation output of the gas fired thermal power project. In addition, minimum long term contracted electricity output would now run for a period of 15 years (instead of 10 years) from the date the project is put into electricity generation operation and participates in the electricity market.
A stronger and longer offtake commitment would be positive move for implementation of gas-fired power projects in Vietnam.
Norton Rose Fulbright is not licensed to practice Vietnam law and does not provide advice on Vietnam law matters. Any comments or analysis provided herein are for general informational purposes only and should not be construed as legal advice under Vietnam law. For formal advice on Vietnam legal issues, please consult a qualified Vietnam law firm or practitioner.