The evolving situation across the Middle East continues to impact global supply chains, projects and commercial relationships. Many businesses are therefore reviewing their contractual positions and considering how disruption may affect performance, risk allocation and dispute exposure.
We have prepared practical guidance to support businesses in navigating these challenges. The update outlines how commonly used contractual mechanisms may operate in the current environment, including force majeure, material adverse change provisions, extensions of time, termination rights and limitations on liability, with specific observations across English law, UAE onshore law, DIFC and ADGM frameworks. It also highlights the importance of early action, disciplined record keeping and carefully managed communications to protect legal and commercial positions.
Key takeaways
- Understand the governing law of your contract
The availability and scope of relief varies significantly across legal systems. For example, force majeure may only apply if expressly drafted under English and ADGM law, whereas it is codified under UAE onshore and DIFC law, subject to specific thresholds. - Review force majeure and risk allocation clauses closely
Whether the current conflict qualifies as a force majeure or similar event will depend on the precise wording of the clause, including how events such as war, armed conflict or government action are defined and whether causation can be established. - Comply strictly with notice and procedural requirements
Many contracts impose tight notification deadlines and formal requirements. Failing to follow these steps correctly may undermine a claim for relief or an extension of time, particularly under English law–governed contracts. - Assess alternative contractual protections
Where force majeure relief is not available, other mechanisms—such as material adverse change provisions, extensions of time or termination rights—may offer partial relief, depending on the circumstances and drafting. - Preserve evidence and maintain contemporaneous records
Accurate records of disruption, delay, mitigation steps and actual losses suffered will be critical to substantiating claims, managing exposure and defending positions if disputes arise. - Reserve rights clearly and appropriately
Parties should expressly reserve specific contractual and legal rights while issues are under review. Generic or open ended reservations may be ineffective, particularly under English law. - Manage communications and commercial discussions with care
Good faith obligations may apply in certain jurisdictions, and “without prejudice” protections are not universally recognised. Parties should approach negotiations and correspondence strategically to avoid unintentionally prejudicing their position.