Electricity (Amendment) Rules, 2026

The Electricity (Amendment) Rules, 2026 (the Electricity Amendment Rules) were announced by India’s Ministry of Power on March 13, 2026. The Electricity Amendment Rules amend Rule 3 of the Electricity Rules, 2005 which sets out the requirement for a captive generation plant.

The Electricity Amendment Rules are not intended to implement new regulations but rather are intended to address structural frictions that were holding back development and financing of generation assets. The Electricity Amendment Rules are well-timed, coming at a juncture where group captive renewable energy projects have become the preferred mechanism for commercial and industrial consumers and the captive power sector has grown considerably in both scale and complexity in the last decade.

Electricity Rules, 2005

By way of background, the Electricity Act, 2003 recognized captive generation as a statutory right and enable captive users to receive benefits such as open access and exemptions from cross-subsidy charges and other surcharges; however it did not set out an objective criteria for determining what constitutes “captive generation”. This presented a risk that large consumers could set up nominal equity structures and avoid system charges.

The Electricity Rules, 2005 were thus enacted to set out an objective criteria which would reduce discretionary interpretation regarding whether a plant was being utilized for genuine self-use generation and encourage private investment in captive plants.

The Electricity Rules, 2005 had to cater for different structures through which genuine captive generation was being achieved – for example, through cooperative-based captive plants, group captive models and captive plants owned by special purpose vehicles that served multiple users.

Rule 3 of the Electricity Rules, 2005 therefore set out the criteria for what constituted a “captive generation plant”. In the case of a power plant, the requirements were that:

  • not less than 26 percent of the ownership of the power plant should be held by captive users; and
  • not less than 51 percent of the aggregate electricity generated in such plant (determined on an annual basis) should be consumed for captive use.

If the power plant was owned by a registered co-operative society, then the above conditions would need to be satisfied collectively by the members of such co-operative society.

If the power plant was owned by an Association of Persons, the captive user(s) would need to hold not less than 26 percent of the ownership of the plant in aggregate and such captive user(s) would need to consume not less than 51 percent of the electricity generated (determined on an annual basis) in proportion to their shares in ownership of the power plant within a variation not exceeding ten per cent.

If the power generation asset had multiple units of which only some (but not all) units are intended for captive generation, the above rules around minimum ownership and minimum electricity consumption would apply in respect of the units that were intended for captive generation.

Rationale for revisions to Rule 3 of the Electricity Rules, 2005

Rule 3 of the Electricity Rules, 2005 did not define what constituted “ownership”, i.e. whether ownership was legal title only or also beneficial interest or whether ownership could be indirectly held. The electricity regulators and distribution companies in India preferred narrow interpretations (for example, only direct equity in the generating company would satisfy the test and consumption of power by an affiliate of the owner of the captive generation plant would not qualify) whereas sponsors and consumers argued for broader interpretations (for example, ownership could be through group entities, indirect holdings, beneficial interest etc.). Similarly, in relation to the 51 percent consumption test, the Electricity Rules, 2005 did not specify the units of measurement, i.e. how the consumed electricity was to be quantified. Distribution companies (DISCOMs) and regulators often argued for actual energy consumption, while some captive structures were designed around capacity entitlements. This forced the state electricity regulatory commissions (SERC) and courts to fill the gaps through interpretation and apply proportionality tests (e.g. is a captive user’s use of electricity proportionate to their ownership in the generating plant).

In its 2023 judgment in Dakshin Gujarat Vij Company Limited v. Gayatri Shakti Paper, the Supreme Court of India clarified that the Electricity Rules, 2005 only recognized two forms of captive use: a single captive user and group captive users (which were limited to co-operative societies and association of persons). It further clarified that companies and special purpose vehicles constituted association of persons (so sponsors and developers could no longer argue that corporate special purpose vehicles were exempt from the abovementioned proportionality tests).

The Supreme Court formulated the unitary qualifying ratio (UQR) and held that the 26 percent ownership requirement and 51 percent consumption requirement were not independent thresholds but were part of one composite test, so for every 1 percent of ownership a captive user must consume c.1.96 percent of the electricity generated (i.e. 51 percent divided by 26 percent) subject to a ± 10 percent variation which was permitted under Rule 3 of the Electricity Rules, 2005. This also meant that failure by one of the users to meet the composite test could potentially render the entire plant non-captive, exposing all users to a cross subsidy surcharge (CSS) and an additional surcharge (AS) liability (discussed below). The captive qualification would be tested on a financial year by financial year basis, and both ownership and consumption requirements would need to be met within the same year. There was no implied restriction on change of ownership as long as the ownership and consumption tests were satisfied.

The Electricity Amendment Rules moves away from the UQR framework and provides a statutory framework which is better suited to the commercial realities of captive power generation by fully substituting Rule 3 of the Electricity Rules, 2005.

Rule 3 under the Electricity Amendment Rules

Under the new Rule 3, in order for a power plant to qualify as a “captive generating plant” under the Electricity Act, 2003, not less than 26 percent of the ownership should be held by the captive user(s) and not less than 51 percent of the aggregate electricity generated in such plant during a financial year should be consumed for captive use.

Ownership requirements

This requirement is consistent with the original Rule 3 under the Electricity Rules, 2005. However, the new Rule 3 now defines “ownership” in a power plant to mean proprietary interest and control, or equity share capital carrying voting rights, held either directly or through a person’s subsidiaries, holding company and any other subsidiary or subsidiaries of such holding company.

The term “captive user” is now defined to mean an end user of the electricity generated in a captive generating plant and includes a person or group of persons who consume such electricity either directly or through an energy storage system used for storing energy generated from such captive generating plant.

If a captive user is a company, then the definition would include its subsidiaries, its holding company, and any other subsidiaries of such holding company (all these would be collectively treated as a single captive user). This has the positive impact of facilitating group captive renewable structures across group entities. This shift from individual proportionality to a collective threshold substantially mitigates the counterparty risk that previously characterised group captive structures, where the non-compliance of a single participant could jeopardise the captive status of the entire plant.

Consider a scenario where a holding company has three subsidiaries that consume power but it is not economically viable for any one of them to commit to the capex of a fully captive plant. In this case, if the three subsidiaries set up a special purpose vehicle (SPV) where they collectively own at least 26 percent of the SPV (with the remainder held by a third party developer), then under the new Rule 3 the three subsidiaries would be deemed to be a single captive user (even if individually they own less than 26 percent of the SPV) because they belong to the same corporate group.

An SPV is now expressly defined in the Electricity Amendment Rules as a legal entity set up solely to own, operate, and maintain a generating station, and which does not carry on any other business or activity. An SPV is now treated as an “association of persons”.  This statutory definition puts an end to the differing views across SERCs on whether generating stations held through SPVs should follow company-level or association of person-level captive rules, ensuring that all “association of persons” provisions (including proportionate consumption requirements) apply uniformly to SPV structures.

In the above example, if the generation station owned by an SPV has two 50MW units generating power and only one (not both) units are identified for captive use, then the 26 percent ownership requirement would be applied proportionately to the one 50MW unit that is identified for captive use (so the ownership requirement would be 13 percent rather than 26 percent). Similarly, the 51 percent consumption test would apply only to the one 50MW unit.

As well, in the above example if the power plant is set up by a registered co-operative society, then the 26 percent ownership and 51 percent consumption test would need to be satisfied collectively by the members of the co-operative society.

Consumption requirements

In relation to the 51 percent consumption test regarding a plant set up by an “association of persons”, for each individual user within such association of persons the captive consumption calculation shall only be up to 100 percent of such individual user’s proportionate consumption calculated with reference to its share of the ownership of the power plant. So, in the above example, if an individual user owns 10 percent of the power plant, the percentage that would be applied towards satisfaction of the 51 percent consumption test would be (51 percent / 26 percent) x 10 percent.

The above proportionate consumption test would not apply if a captive user holds more than 26 percent ownership in the power plant.

If the ownership pattern of the power plant varies during the financial year, the proportionate consumption of each captive user would be determined on the basis of the weighted average shareholding of such captive user during the financial year.

Verification

The Electricity Amendment Rules implement a dual verification structure to assess compliance with the above ownership and consumption requirements. For captive projects where the power project and consumers are based within the same state, the verification would be done by an agency designated by the state (e.g. the relevant state loan dispatch centre or SDLC). However if the captive project and consumers are in different states, this verification would be done by the National Load Despatch Centre or NLDC).

Cross-subsidy charges and additional surcharges

A cross-subsidy charge is payable whenever a consumer procures power through open access instead of the local DISCOM. It is intended to compensate the DISCOM for loss of cross subsidy revenue embedded in its retail tariff structure when a large consumer opts to source power through open access rather than through the grid.

Additional surcharges would be payable to a DISCOM to enable them to fund the fixed capacity charges that they continue to incur under long-term power purchase agreements they have entered into in anticipation of meeting demand. These fixed capacity charges would be payable notwithstanding that demand is now reduced because the relevant consumer has now opted to source power through the open access route, thus leaving the DISCOM with stranded capacity.

For captive users, if the minimum captive consumption requirement is not met during any period, a cross-subsidy surcharge and an additional surcharge shall be levied on such consumption. In the case of a power plant set up by an association of persons, any consumption by an individual captive user in excess of one hundred percent of its proportionate consumption (see calculation above) shall be subject to a cross-subsidy surcharge and an additional surcharge on such excess consumption. However, such excess consumption still counts towards determining whether the plant meets the minimum 51 percent collective captive consumption requirement, thus ensuring that the group captive model retains its intended flexibility.

Captive use through energy storage systems

The inclusion of an energy storage system in the definition of captive user is significant since it decouples consumption from real time generation. Energy stored from a captive generation plant and consumed later would retain its captive character. This enables round-the-clock (RTC) and firm and dispatchable structures to be introduced within captive generation models, although seamless implementation of these changes at the state level will require SERCs to issue corresponding amendments to their respective captive regulations.

The Electricity Amendment Rules do not address the distinct practice of banking of energy, whereby surplus captive generation is injected into the grid and later drawn back by the captive user under banking arrangements permitted by the relevant SERC. DISCOMs have historically disputed whether banked energy retains its captive character upon being drawn, arguing that re-injection and re-drawing of power breaks the chain of captive consumption. This issue remains unresolved under the Electricity Amendment Rules.

Norton Rose Fulbright is not licensed to practice Indian law and does not provide advice on Indian law matters. Any comments or analysis provided herein are for general informational purposes only and should not be construed as legal advice under Indian law. For formal advice on Indian legal issues, please consult a qualified Indian law firm or practitioner.