Information correct as of May 2026.
Vietnam’s offshore wind potential and PDP8
Vietnam has one of the most extensive and attractive offshore wind resources in Southeast Asia, driven by its long coastline of more than 3,200 km, strong and consistent monsoon wind regimes, and large areas of shallow and mid‑depth waters suitable for both bottom‑fixed and floating offshore wind technologies.
The best‑suited offshore wind sites are concentrated along the South Central and Southern coasts, particularly Binh Thuan, Ninh Thuan, Ba Ria–Vung Tau, Ca Mau and Soc Trang, where average wind speeds are among the highest in the region, seabed conditions are relatively favourable, and proximity to major load centres in southern Vietnam improves long‑term transmission economics.
Following the promulgation of the Electricity Law on 30 November 2024 (effective from 1 February 2025), the Prime Minister issued Decision No. 768/QD TTg on 15 April 2025, approving the revised National Power Development Plan VIII (PDP8) for the period 2021–2030, with a vision to 2050. This decision replaces the earlier Decision No. 500/QD TTg dated 15 May 2023.
Under the revised PDP8, offshore wind capacity is projected to reach between 6,000 MW and 17,032 MW by 2035.
Decree 58 and offshore wind regulatory framework
Decree No. 58/2025/ND CP
Decree No. 58/2025/ND CP (Decree 58) came into effect on 3 March 2025 and establishes a detailed regulatory framework for renewable and new energy projects, with a particular focus on offshore wind power. Under Decree 58, offshore wind projects are defined as wind projects located beyond 6 nautical miles from the shoreline.
Foreign ownership and joint venture requirements
Foreign investors may own up to 95% of an offshore wind project. Foreign investors must enter into a joint venture with a state owned enterprise or an enterprise in which more than 50% of charter capital or voting shares are held by a wholly state owned enterprise. Any transfer of foreign ownership interests remains subject to regulatory approvals.
Incentives for offshore wind projects
- Land and sea area fee incentives: To incentivise offshore wind development, Decree 58 provides an exemption from land/sea area use fees for up to 3 years during construction and a 50% reduction in sea area use fees for the following 12 years. There are also subsequent land use fee exemptions or reductions in accordance with Vietnam’s land laws.
- Contracted output and revenue support: A minimum contracted output (Qc) of 80% per year (based on forecast net generation) for 15 years applies. A proposal to provide a more favourable Qc regime for offshore wind is under consideration and pending approval. The 15 year duration broadly aligns with the debt tenors relevant to financings for offshore wind projects and early equity recovery period for large offshore wind projects and mitigates against revenue risks resulting from curtailment and grid constraints.
- Additional incentives: Further incentives include import duty exemptions for equipment, eligibility for government supported funding; and access to incentives under the Investment Law, as renewable energy is classified as a specially incentivised sector.
Centralised project approval and investor selection
By way of background, in Vietnam, power projects may be developed under either the Independent Power Producer (IPP) model or under the Public-Private Partnership (PPP) Law that came into effect in Vietnam on 1 January 2021 (the PPP Law). The PPP Law consolidates the law in relation to public projects and is intended to promote greater collaboration between the public and private sectors, including in the development and implementation of large-scale renewable energy projects such as offshore wind.
Projects developed under the IPP model are primarily selected and approved at the provincial level, with oversight and policy guidance from Ministry of Industry and Trade (MOIT). The projects must be listed in - or aligned with - PDP8. The provinces are responsible for integrating power projects into their provincial master plans, including land-use and environmental zoning. For most IPP projects, provincial governments handle investor selection, project approvals, land allocation and permitting, however this does not apply to offshore wind projects.
On 22 October 2025, the MOIT issued Report No. 246/BC BCT, calling for higher level guidance to remove obstacles and accelerate offshore wind development. Subsequently, a National Assembly Resolution, passed on 11 December 2025, introduced new mechanisms for national energy development (the New Resolution). Under the New Resolution:
- The Prime Minister will centrally approve offshore wind projects and investor selection for projects commencing operation during 2025–2030.
- No land use auction or investor selection tender is required, provided that the project meets national defence, security, sovereignty and marine environmental conditions and is included in the relevant power development plan.
For projects expected to commence operation during 2031–2035, the approval authority shifts to the provincial People’s Committee where the offshore substation is located, provided that written opinions must still be obtained from relevant ministries and authorities.
The New Resolution only provides a general framework for offshore wind development. More detailed guidance – covering matters such as licensing procedures and roles of the relevant competent authorities – is expected to be issued by the government, and its practical implementation remains to be seen.
Survey rights and early stage development
Offshore wind development in Vietnam has been materially affected by delays in the issuance of marine survey rights, without which developers cannot prepare bankable foundation designs, cable routes or reliable capital expenditure models. Some progress was seen in November 2025 with the Nam Bo offshore wind project in Vinh Long province being granted a sea area allocation decision for the purpose of conducting a survey.1 In April 2026 a site survey licence was also obtained by Pacifico Energy for a 500 MW offshore wind project in Ba Ria–Vung Tau.2 These developments mark the first tangible progress toward commercial offshore wind development.
Infrastructure and supply chain challenges
Despite progress on surveys, key structural challenges remain – e.g. lack of adequate port infrastructure capable of supporting offshore wind installation by 2030 and broader supply chain capacity constraints, particularly for foundations, vessels and specialised equipment. In addition, the legal and regulatory framework for Vietnam’s offshore wind sector remains under development and market participants are engaged in active dialogue with the Vietnam government on a range of issues impacting development, including the issuance of survey rights, cost recovery mechanisms, technical and environmental standards.
Bankability challenges under EVN PPAs
The bankability of power purchase agreements (PPAs) with Vietnam Electricity (EVN) remains a key concern, particularly for offshore wind projects with high capital costs. Key challenges include:
- No sovereign guarantees: Traditional PPAs with EVN do not include sovereign guarantees for payment obligations. This has made it difficult for developers to secure international project finance, especially from commercial banks.
- Curtailment risk: Grid congestion, particularly in southern Vietnam, often leads to curtailment. PPAs often do not compensate for curtailed energy, affecting revenue predictability.
- No deemed dispatch: PPAs may not contain deemed commissioning or deemed dispatch payments if the generator is unable to generate electricity for any other reasons outside of its control.
- Liquidated damages risk: The PPA may not cover liquidated damages for delay in completion. Whilst at first instance this appears beneficial to the generator under the project, this would enable EVN to claim general damages at law for a breach of the agreed implementation schedule. There would likely be no cap on liability under the PPA. This reduces the certainty and ability of the generator to quantify its potential liability.
- No termination compensation: The generator would need to rely on its ability to claim general damages from EVN if the PPA terminates due to a breach by EVN. Whilst this would be subject to Vietnamese law, there is unlikely to be any compensation available to the generator if the PPA terminates due to force majeure.
- Change in law risk: The PPA does not have a specific provision to deal with the expenses or arising obligations due to changes in law. Vietnamese laws and regulations have changed from time to time to reflect changes to the government’s national strategies. Hence, the long-term investor of power projects may face a higher risk of a change in law.
Circular 12/2025/TT-BCT
Circular 12/2025/TT-BCT (Circular 12) came into effect on 1 February 2025 and introduced a more flexible PPA template in relation to projects that are developed under the IPP model, allowing parties to negotiate key terms such as performance commitments, dispatch and operation, billing and payment, force majeure and dispute resolution. Under Circular 12 tariffs are calculated based on “reasonable and legitimate costs” over the economic life of the project. These include capital costs, O&M, fuel costs (if applicable), and other allowable expenses. The IRR is capped at 12%.
The tariff is comprised of a fixed price (which covers capital recovery and fixed O&M costs) and a variable price (which would include fuel costs and variable O&M for thermal power projects). Costs relating to interconnection may also be included if agreed between the developer and EVN.
A temporary tariff may be agreed pending final negotiations to enable the developer to agree debt sizing with its financiers. The PPA tariff must be benchmarked against the “base year” of the electricity generation pricing framework (i.e. year for which the electricity generation pricing framework issued by MOIT is available for use to determine the tariff). If no framework exists for the base year, the most recent applicable year is used for comparison.
While Circular 12 is an improvement, further enhancements will likely be required for offshore wind to achieve full project finance bankability.
Norton Rose Fulbright is not licensed to practise Vietnamese law and does not provide advice on Vietnamese law matters. Any comments or analysis provided herein are for general informational purposes only and should not be construed as legal advice under Vietnamese law. For formal advice on Vietnamese legal issues, please consult a qualified Vietnam law firm or practitioner.