On 3 June 2026, Lombardy adopted the first regional law in Italy specifically addressing the development of data centers. In force since 5 June 2026, following its publication in the Official Regional Bulletin, the law sets out a comprehensive framework for siting, permitting and monitoring new facilities, and works alongside the national regime introduced by the so-called Decreto Bollette (Decree-Law No. 21/2026, converted into Law No. 49/2026).
Although based on Draft Law No. 150 (presented in November 2025), the final version goes noticeably further. It introduces stricter environmental safeguards, a new system of incentives, and more structured coordination mechanisms for larger projects.
Key changes compared to the original draft
Broader policy objectives and stricter environmental approach
The final law retains the original objectives — economic growth, sustainability and energy efficiency — and adds explicit priorities relating to biodiversity, landscape, water resources, and alignment with local infrastructure capacity.
The location strategy remains focused on brownfield and regeneration areas, but with a more practical emphasis. Projects are now expected to take account of proximity to existing grid infrastructure, reflecting increasing constraints on connection capacity.
The approach to energy has also evolved. Rather than requiring only renewable sources, the law adopts a broader concept of carbon-neutral energy. At the same time, water use is more tightly regulated, with strict limits on withdrawals from drinking water networks and a clear preference for recycling and alternative cooling solutions.
A new incentive framework
One of the most important additions is the introduction of a structured set of incentives, which was not included in the draft. Projects that meet sustainability and siting criteria may benefit from faster procedures, priority access to regional funding, reductions in certain construction charges (up to 30%), and significantly lower parking requirements.
In practice, these measures make site selection a strategic decision: choosing a compliant location can materially improve both timelines and costs.
Higher costs for greenfield development
The law also strengthens disincentives for projects on agricultural land. The surcharge on construction contributions increases from 50% in the draft to 100%, rising to 200% in areas within regional parks and nature reserves (under Regional Law No. 86/1983). By contrast, developments on brownfield sites may benefit from reduced contributions where remediation costs are borne by the developer.
More structure for large-scale projects
For projects above 10 MW, the law replaces the draft's general "co-planning" approach with a more formal coordination process. A multi-authority conference will assess impacts and lead to a supra-municipal agreement, including compensation measures where needed. Larger projects (above 50 MW) involve direct regional coordination.
Projects can be approved in functional phases. Each phase proceeds only if the required energy and water infrastructure is actually available, as verified during the compatibility assessment and reflected in the supra‑municipal agreement.
New procedural tools
Two practical elements complete the regime. First, a mandatory energy report must be submitted with project applications, covering energy sourcing, efficiency and, where relevant, heat recovery. Second, a regional one-stop shop (“Sportello regionale per i centri dati”), already envisaged in the draft, has now been redesigned to manage the single-permit procedure introduced by the Decreto Bollette.
Transitional provisions
Applications already pending are not suspended. For authorisation matters, the new regime under this law applies only to applications submitted after publication in the Official Regional Bulletin of the regional implementing guidance for the single-permit/AIA process, while pending AIA proceedings continue to be handled by the competent province or the Metropolitan City of Milan.
For the supra-municipal coordination process, the new rules apply only to applications submitted after publication in the Official Regional Bulletin of the regional decision setting out the procedure and criteria for compensatory measures.
Municipalities have 365 days from entry into force to identify or update disused, degraded or under‑utilised areas. Failure to meet this deadline does not prevent the submission or processing of project applications.
In practical terms
For operators, the main implication is clear: early choices on location and energy strategy are now critical. Projects that align with the law's priorities can move faster and at lower cost, while others face significantly higher charges and more complex procedures, particularly at larger scale.
For municipalities, the focus will be on mapping suitable sites and managing the new compensation mechanisms introduced by the law.
Overall
The new law reflects a more proactive approach: Lombardy is not only setting rules for data centers but also shaping where and how they are developed.
A permanent steering committee (“Cabina di regia”) will monitor the sector’s evolution and cumulative impacts — energy, water, land use and heat — including network capacity, and may propose regulatory updates.
Much, however, still depends on the implementing measures that the Regional Government must adopt within sixty days, covering sustainability thresholds, incentive criteria, and the coordination process for larger projects. Until then, the full picture remains incomplete. We will provide updates as these measures are published.