This article was written in collaboration with Partners Karan Mitroo, M. Arun Kumar and Ankita Parasar, Senior Associate, Ahona Pal and Associate, Kopal Kesarwani of JSA Advocates & Solicitors.

CERC Order

The Central Electricity Regulatory Commission (CERC) issued a significant order on 10 July 2026 (the Order) aimed at addressing the growing disconnect between renewable energy projects that have obtained Inter-State Transmission System (ISTS) connectivity on the basis of Letters of Award (LoAs) and those that have subsequently progressed to execution of power purchase agreements (PPAs).

The Order introduces a one-time framework for projects holding LoA-based connectivity where PPAs have not been signed within 12 months of the relevant LoA, with the objective of releasing scarce transmission capacity tied up by the projects that may never reach commercial operation, while providing developers with alternative pathways to preserve or repurpose their connectivity rights, by availing one of the four options discussed below.

Background: Why has the CERC intervened?

Under India’s CERC (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 (GNA Regulations), power generation companies can access the ISTS without identifying point-to-point transmission paths in advance.

Government offtakers in India (such as SECI, NTPC, SVJN etc.) conduct renewable energy tenders and auctions and issue LoAs to successful bidders. One of the routes under the GNA Regulations through which the successful bidders can apply for grid connectivity to the ISTS is via the submission of LoA issued by the government offtakers. The grid connectivity can be achieved at an earlier stage of the project development, even before project development milestones are achieved. A key reason for this is that the capacity of the ISTS is limited. Large ISTS-connected renewable projects may require development of new sub-stations, augmentation of existing infrastructure and expansion of transmission lines etc., which may take considerable time to effectuate. If connectivity were granted only after all project milestones were completed, this would likely result in a mismatch between the timing of completion of the project and the completion of the transmission system. Obtaining connectivity in advance effectively reserves a place for the project in the transmission connectivity allocation queue maintained by the Central Transmission Utility of India Limited (CTUIL) and also enables CTUIL to undertake transmission planning and notify project developers of expected timelines in relation to readiness of the ISTS for evacuation of the power.

The above approach is predicated on the government offtaker (e.g. SECI) entering into PPAs with the project developers and further entering into back-to-back power sales agreements (PSAs) with the ultimate buyer of the power (e.g. state distribution companies (or discoms)) after grant of the LoA. However, based on the data reviewed by CERC, a large number of projects that have obtained an LoA have not progressed to entering into a PPA. There are a number of factors that have resulted in this – e.g. a lower demand for standalone solar projects with a greater preference for projects that address states’ peak power requirements (e.g. round-the-clock and firm, dispatchable renewable energy projects and storage backed projects), as well as lower tariffs discovered in Iater auction rounds which make later projects more economically attractive compared to older projects for which LoAs have been granted.

Unutilised connectivity

CERC has noted in the Order that while the total LoAs issued for the period from 2019 to June 2025 were for an aggregate capacity of 40,420 MW, PPAs were only entered into for an aggregate capacity of 2,338 MW. In this period connectivity was granted for projects for an aggregate capacity of 22,054 MW but no PPAs have been entered into in relation to these so far (although the government offtakers anticipate PPAs would be entered into for 2,490MW capacity).

Notwithstanding the delay in entering into PPAs however, the projects retain connectivity rights. As a result, transmission capacity remains tied up even though the projects are not progressing.

In the above circumstances, the Order attempts to preempt a situation where connectivity that has been granted to projects remains stranded. To avoid a scenario where connectivity remains blocked by LoAs which may never materialize into power generating assets, it is appropriate to consider mechanics that would enable such connectivity to be released.

Scope of the CERC order

Based on recommendations received from the Ministry of Power and the Ministry of New and Renewable Energy, the CERC has set out the below mechanics for treatment of connectivity granted under GNA Regulations where PPAs (for full capacity or part capacity) have not been signed within 12 months from the date of issuance of the relevant LoAs. The Order takes into account the LoAs issued by the government offtakers (SECI, NTPC, NHPC and SVJN) between January 2019 and December 2025. The government offtakers are required to provide a list of the LoAs to CTUIL, based on which CTUIL would then publish details of the connectivity provided to the projects under such LoAs and allow opportunities to the project developers to verify the published information and report any discrepancies or seek necessary corrections.

The projects that are in the final list prepared by CTUIL would, within 60 days of the issuance of the list, be required to opt for one of the following courses of action. If the project developer fails to opt for one of the options within 60 days, connectivity shall continue to be governed in terms of the GNA Regulations (deemed to be under Option 4 below) and the developer shall lose its right to choose an option under the Order. The options listed below are voluntary and it would be open to a project developer not to exercise any of these options:

  1. Exit from the LoA route, without surrendering the connectivity (Option 1)
  2. Substitution of the LoA with a PPA signed under another LoA (Option 2)
  3. Surrendering of such connectivity with return of Conn-BGs (Option 3)
  4. Continuing to be governed in terms of the GNA Regulations (Option 4)

There is no application fee applicable for exercising these options. Further, a No-Objection Certificate (NOC) from the concerned government offtaker is required to seek conversion under Option 1, Option 2 and Option 3. The relevant government offtaker is required to process an application for NOC either by clearly communicating the NOC or rejecting the application within 15 days of receipt of such application.

Option 1 – Exit from the LoA route, without surrendering connectivity

Any project developer intending to exit from the LoA route must first obtain a NOC from the relevant government offtaker which had awarded the LoA. Such NOC from the offtaker must certify the non-signing of the PPA. The exercise of this option would require the project developer to submit a performance bank guarantee aggregating to INR 8,00,000 per MW to CTUIL. Further, the project developer must notify a new scheduled commercial operation date (SCOD) for the project which must be no later than 24 months from the date of acceptance by CTUIL of the exercise of this option and the firm start of connectivity (i.e. the final confirmed date from which a power generator is entitled to inject power into the ISTS network/date of effectiveness of GNA), whichever is later.

If Option 1 is exercised, then:

  • under Regulation 5.8(xi) of the GNA Regulations, the project developer must submit evidence of land acquisition or land rights sufficient for the project by the later of:

    • (i) 12 months from the date CTUIL issues the revised in-principle intimation or revised final intimation to the project developer upon exercising this Option 1; and
    • (ii) 9 months from the date CTUIL communicates the tentative coordinates of the connectivity substation to the project developer under Regulation 10.5(b) of the GNA Regulations.

This mechanism enables the project developer to have sufficient information about the location of the grid connection before being required to finalise land arrangements; and

  • the project developer must also submit financial closure documents pursuant to Regulation 11A(2) of the GNA Regulations (e.g. executed facility agreement, board approvals, evidence of satisfaction of conditions to utilization etc.) by the later of:

    • (i) 18 months from the date CTUIL issues the revised in-principle intimation or revised final intimation to the project developer upon exercising this Option 1; and
    • (ii) the regular timeline under Regulation 11A(2) of the GNA Regulations.

    With these mechanics, the CERC would effectively grant projects a fresh 18 month period to achieve financial close.

Option 1 does not require the project developer to provide fresh bank guarantees. The connectivity bank guarantees (i.e. the Conns-BG1, Conns-BG2 and Conns-BG3) that are already in place would remain in place until the project achieves the commercial operation date (COD). The performance bank guarantee (PBG) submitted by the project developer to secure its obligations would be released after a 1 year period following the COD for the amount corresponding to the actual generation capacity achieved at COD.

Failure to meet the above conditions in relation to land acquisition and financial closure documents within the stipulated timeline may result in revocation of the connectivity and shall entitle CTUIL to revoke the Conns-BG. Similarly, a failure to achieve full quantum of COD may result in an encashment of the full or proportionate amount of the PBG furnished under this Option 1.

The milestone of submission of land documents, financial closure and COD under this option may be extended upon payment of the applicable compensation charges, as per the provisions of the GNA Regulations or as indicated by way of a separate order.

Once an entity has exited from the LoA route, such LoA shall become an invalid document for purposes of obtaining connectivity (or to convert connectivity from the land route or land bank guarantee route to the LoA route). Further, where a PPA has not been signed under the LoA and a period of 12 months has also not elapsed from the date of issuance of the LoA, then, if the respective government offtaker permits, such entity may also opt to exit from the LoA route and exercise this Option 1.

Option 1 would allow a developer to pivot away from the original government-backed LoA/PPA model and pursue alternative options such as private offtake or merchant strategy.

Option 2 - Substitution of the LoA with a PPA signed under another LoA

An entity may also opt to substitute the original LoA (LoA1) that formed the basis for obtaining original connectivity or for converting its connectivity from the land route or land bank guarantee route to the LoA route. This LoA1 may be replaced with another LoA (LoA2) against which a PPA has already been signed with a government offtaker or a distribution licensee or an authorized agency on behalf of a distribution licensee in India. This option may be exercised in a scenario where a PPA was signed by the project developer itself or by its parent, subsidiary or another subsidiary of the same parent company. This is however subject to the condition that the SCOD under the PPA should not be later than 30 months from the date of conversion under this Option 2. The Order notes that ‘subsidiary’ mentioned shall be as defined in the (Indian) Companies Act, 2013.

If the contracted capacity under the PPA signed in relation to LoA2 is lower than quantum of connectivity granted based on LoA1, then the balance connectivity capacity would need to be converted under either Option 1, Option 2 or Option 3 of the Order. Further, if the installed capacity under the PPA in relation to LoA2 is more than the proposed contracted capacity under LoA1 and the entity wishes to retain connectivity procured based on LoA1 for such excess installed capacity, the entity may avail Option 1 and submit the PBG for the quantum of the excess capacity, such that SCOD shall be aligned for the entire converted quantum and shall not be longer than 30 months from the date of conversion. In case the project developer does not exercise its right to convert the excess installed capacity for which connectivity was granted under LoA1, such quantum of connectivity shall be deemed surrendered in accordance with Option 3 of the Order.

In addition, in case the contracted capacity under the PPA in relation to LoA2 is greater than the quantum of connectivity which was granted under LoA1, the conversion allowed under this Option 2 shall only be up to the quantum of connectivity granted under LoA1. If the PPA under LoA2 was also utilised to obtain another connectivity approval, such connectivity must also be converted under Option 1 or Option 3, failing which it will be considered as deemed surrendered.

The Order also prescribes a separate process for multi-located projects, i.e. where LoA1 was used to obtain connectivity for projects at multiple locations, but the PPA executed pursuant to the LoA2 related to single location (or vice versa) and where both the LoA1 and the corresponding PPA are to be used to procure connectivity for projects at multiple locations.

The Order clarifies that upon exercising Option 1 or Option 2, there shall not be any change in the firm start date of connectivity for project developers to whom the firm start date of connectivity has already been issued.

The milestones in relation to land acquisition and financial closure documents and COD (and consequences if these are not achieved by the agreed timeline) continue to apply as per Regulation 11A(2) of the GNA Regulations.

The Order also provides that LoA1 shall become an invalid document to obtain any other connectivity or to convert from land or land bank guarantee route to LoA route.

Option 3 – Surrendering connectivity and return of Conn-BGs

A project developer may also opt to surrender the connectivity capacity granted by CTUIL, in whole or in part.

In case of surrender of a part of the connectivity, the project developer may opt for either Option 1 or Option 2 above to convert the balance of the connectivity, on the condition however that the quantum of connectivity converted under Option 1 or Option 2 above shall not be less than 50 MW. Further, it shall be mandatory for the entity to procure NOC from the relevant government offtaker seeking such surrender of connectivity and submit the same with CTUIL. However, such NOC shall not be required in case of a deemed surrender of connectivity under the Order.

After surrender of the connectivity under this Option 3, within one month of such surrender CTUIL would offer such (now available) connectivity to the other entities to whom in-principle or final connectivity has been granted in the same cluster of sub-station in which connectivity has been made available under Option 3, or conduct an open auction process for the award of such connectivity. The process for undertaking such an auction has also been detailed under the Order.

Option 4 - Continuing to be governed under the GNA Regulations

The project developer may also choose to continue to be treated under the GNA Regulations by notifying CTUIL of its decision within 60 days of issuance of the above list by CTUIL.

The GNA Regulations provide provisions for surrender of connectivity at different stages of connectivity application and also provide for the appropriate provisions on relinquishment of connectivity and revocation of connectivity for not achieving SCOD in accordance with the terms of GNA Regulations.

PPA executed for the part quantum of connectivity

In a scenario where a PPA has been executed for a part of the quantum of connectivity capacity, the project developer shall be entitled to convert the balance quantum of connectivity under Option 1, Option 2 or Option 3. Further, if a PPA has not been signed and a part of the quantum of the connectivity has been converted under Option 1, then the balance quantum must be dealt with under either Option 2 or Option 3. An entity cannot retain a portion of its connectivity under the GNA Regulations under Option 4 and also seek the flexibility provided under the Order for the remaining quantum.

Key concerns raised by industry players

Several developers, industry associations and renewable energy investors noted their opposition to the draft proposal released by CERC for commentary (and many of those concerns remain relevant even after the final order of the CERC) because they viewed it as retrospectively changing the connectivity regime and effectively forcing developers to give up connectivity rights that were validly obtained under earlier rules. A key point highlighted is that although the order from the CERC deals with connectivity granted following issuance of an LoA, it does not address those projects where connectivity has been granted through the land route or land bank guarantee route (i.e. where the grant of connectivity was made on the basis of a project developer having acquired the land or furnishing a bank guarantee as security while it acquires the land). This has led to concerns regarding the inconsistent treatment of similarly placed projects and the continued blocking of transmission capacity by projects outside the scope of the Order.

Some of the stakeholders also suggested that, in the case of Option 2 above, the timeline for SCOD should be aligned with the SCOD specified under the PPA signed in relation to LoA2 (including any extensions granted from time to time) instead of such SCOD being restricted to a 30 month cap from the date of conversion under Option 2.

CERC has ultimately concluded that the broader problem is more serious, particularly with the concern around over 22 GW of connectivity being granted but PPAs for a substantial portion of that capacity not having been entered into. From CERC's perspective, if connectivity remains tied to projects that may never materialise, then new projects with genuine demand cannot access the transmission system.

It should be noted that the Order may be appealed by the industry stakeholders before the Appellate Tribunal for Electricity (APTEL). However, until a specific stay order or dismissal order has been issued by APTEL, the facilities under this Order remain to be applicable to the relevant projects.

Financiers’ perspective

From a project finance perspective, lenders are likely to focus on the conditions attached to conversion of connectivity under the Order, particularly the possibility of revocation of connectivity, encashment of Conn-BGs or forfeiture of PBGs, as these could materially affect the value and bankability of a project. At the same time, the Order also offers flexibility under Option 1, allowing developers to retain connectivity even without an immediately executed government-backed PPA, which could potentially present an opportunity for financiers to switch to merchant revenues, corporate PPAs or any other commercial arrangement.

Norton Rose Fulbright is not licensed to practice Indian law and does not provide advice on Indian law matters. Any comments or analysis provided herein are for general informational purposes only and should not be construed as legal advice under Indian law. For formal advice on Indian legal issues, please consult a qualified Indian law firm or practitioner.