How rising fuel costs might impact principals and contractors

This article was co-authored by Zac Condon.

Background

The Fair Work Commission (FWC) made the Road Transport Contractual Chain Order – Fuel Cost Recovery – 2026 (RTCCO) in April 2026. The Order was a direct response to the fuel supply chain disruption caused by the significant reduction in shipping through the Strait of Hormuz and the ongoing conflict in the Middle East.

RTCCO imposes obligations on "primary parties" and "secondary parties" in road transport contractual chains to adjust the rates they pay — fortnightly or twice per calendar month — to ensure that downstream parties recover the increased cost of fuel.

  • A “primary party” is a party to the first contract or arrangement in a road transport contractual chain — typically the client or principal at the top of the chain.
  • A "secondary party" is a party to a subsequent contract or arrangement in the chain, often involving the parties completing the relevant transport work.
  • In practice, primary parties are the entities that originate the transport task, while secondary parties are the intermediary businesses (such as transport companies and subcontractors).

These adjustments can take several forms, including rate adjustments, fuel levies, or direct reimbursements. Penalties for contravention apply.

RTCCO obligations are tied to a diesel price trigger: they cease to apply if the weekly average national terminal gate price for diesel falls below $2.00 per litre.

There has been some uncertainty about the effect of the RTCCO insofar as it impacts the cost of construction, noting the potential cost escalation that may arise on construction projects in the implementation of the Order. This uncertainty remains given the ongoing geopolitical circumstances in the Middle East.

The Fair Work Commission will hold a hearing on 9 October 2026 to review the RTCCO. The outcomes of that hearing will likely provide some guidance as to the ongoing implementation of the RTCCO and practical effect on the construction industry.

Current status of RTCCO

RTCCO obligations initially switched off on 7 June 2026, within seven weeks of taking effect, after the diesel price fell below the $2.00 threshold.

On 7 July 2026, the FWC Expert Panel confirmed that the clause 4 obligations remain off and that the Panel declined to vary the Order to re-enliven them. Importantly, however, the Order has not been revoked and remains technically in force — it is effectively dormant, with no operative obligations.

On 26 August 2026, the FWC’s Expert Panel held a case management hearing after diesel costs rose above the $2.00 threshold in the week ending 21 August 2026. The issue was that RTCCO contained no clear mechanism for the automatic revival of its obligations.

No definitive decisions were made at the hearing. Instead, it invited interested parties to make submissions and set a procedural timetable for a substantive hearing.

Stakeholders remain divided. The Transport Workers' Union and the Australian Trucking Association submitted that RTCCO should be re-enlivened, while other interested parties submitted that it should be revoked entirely.

Key issues under consideration

Several unresolved questions are now before the Expert Panel:

  • Revival mechanism. RTCCO does not address what happens when the diesel price falls below the $2.00 threshold and then rises above it again. One argument holds that the trigger is exhausted once used. However, another argument claims that the threshold is conditional and capable of being revived.
  • Buffer period. Previously, proposals were made that RTCCO obligations would only cease after the cost of diesel fell below $2.00 for four consecutive weeks, rather than a single week. This remains a live issue.
  • Application to road haulage. The scope of RTCCO's application to road haulage arrangements remains unsettled. This is relevant to construction projects where road haulage forms part of the supply chain.
  • Fixed price lump sum contracts. It is unresolved whether RTCCO applies to fixed price lump sum contracts.
  • Fuel excise relief. The Expert Panel may consider the impact of the phasing out of the Commonwealth's fuel excise relief measures as a factor bearing on whether any variation to RTCCO is warranted.
  • Ongoing geopolitical developments. The continued escalation in the Strait of Hormuz makes it difficult to see how the Expert Panel would accept that the emergency causing RTCCO has passed.

Practical implications

Given the prospect of RTCCO being reinstated, principals and head contractors should consider the following:

Contractual

  • Revived obligations would require primary parties to adjust rates fortnightly to ensure recovery of fuel costs.
  • RTCCO would also require them to take reasonable steps to ensure that secondary parties further down the chain are adjusting their rates, regardless of any direct contractual relationship.
  • It remains unsettled how RTCCO applies to fixed price lump sum contracts, making it difficult to anticipate contractual risk for those arrangements.

Commercial

  • Fortnightly fuel cost pass-through obligations introduce a variable cost element that may be difficult to manage within fixed project budgets.
  • Ongoing and new contractual commitments should anticipate RTCCO obligations, and where possible, contracts should include clauses permitting adjustments or variations to rates in response to regulatory changes.

Compliance

  • Penalties apply for contraventions of RTCCO under section 536NP of the Fair Work Act.
  • The FWC has not, to date, been persuaded by submissions about the difficulties of implementing RTCCO in the construction industry.
  • Primary parties should maintain records of fuel costs, correspondence and documents exchanged within the contractual chain as evidence of compliance, particularly given the "reasonable steps" duty.

Takeaways

The rise of diesel prices above the $2.00 threshold and the ongoing geopolitical circumstances in the Middle East suggest there is a real prospect that the FWC will reinstate its RTCCO obligations.

Organisations involved in utilising road transport contractual chains — particularly principals and head contractors operating under fixed price delivery models — should review their current contractual arrangements to determine what relief may be available if the RTCCO obligations are reinstated. For example, the allocation of risk in respect of changes in law may determine whether relief is available in circumstances of fuel-based cost escalation.

Interested parties should otherwise monitor the outcomes of the Expert Panel's substantive hearing, and ensure they are positioned to comply at short notice if RTCCO’s obligations are revived.