The English courts historically treated a failure to comply with steps in a tiered arbitration agreement as being a matter of the tribunal’s jurisdiction. While there are many examples, the case typically referred to is Emirates Trading Agency v Prime Mineral Exports [2014] EWHC 2104 (Comm).
The question before the court was whether an agreement that the parties would “seek to resolve the dispute or claim by friendly discussion…for a continuous period of 4 weeks” was enforceable, and a condition precedent to arbitration, or otherwise a mere agreement to agree. The court held that the agreement was enforceable because it was complete and sufficiently certain. Relevantly, the court treated it as settled law that, if a party failed to comply with an enforceable condition precedent, the tribunal would lack jurisdiction. Nonetheless, the court held that the condition precedent had in any event been complied with, and so did not consider whether there was any effect on the tribunal’s jurisdiction.
The first English court decision to tentatively tease out the distinction between jurisdiction and admissibility was Tatneft v Ukraine [2018] EWHC 1797 (Comm) in July 2018. In that case, the court dismissed Ukraine’s challenges to enforcement of an award in Tatneft’s favour under the Bilateral Investment Treaty between Ukraine and Russia on the basis that the challenges primarily concerned questions of admissibility, not jurisdiction. This was important because, if not a question of jurisdiction, there would be no grounds for challenging enforcement on the basis of state immunity.
Importantly, in Tatneft v Ukraine, the court delineated the difference between jurisdiction and admissibility as follows: “Issues of jurisdiction go to the existence or otherwise of a tribunal's power to adjudge the merits of a dispute; issues of admissibility go to whether the tribunal will exercise that power in relation to the claims submitted to it”. Issues of admissibility therefore inherently assume that the tribunal is already empowered to hear the claim in question, i.e. that it has jurisdiction – the question on admissibility is rather whether it is appropriate for the tribunal to exercise that power at that time.
The defining moment in English law was the decision in Republic of Sierra Leone v SL Mining [2021] EWHC 286 (Comm) in February 2021. In that case, the award debtor applied to have a London-seated award set aside under Section 67 of the Arbitration Act 1996, contending that the tribunal lacked substantive jurisdiction because the award creditor had failed to comply with pre-conditions to arbitration in a tiered arbitration agreement.
The dispute resolution provisions in Sierra Leone were similar to those in Emirates Trading Agency v Prime Mineral Exports. Before referring a dispute to arbitration, the parties were obliged to endeavour in good faith to reach an amicable settlement of all differences of opinion and disputes for a period of not less than 3 months. The award creditor served a Notice of Dispute on 14 July 2019, triggering the 3 month period for good faith negotiations. However, the award creditor then filed its Request for Arbitration on 30 August 2019, only six weeks later.
After a painstaking review of judicial and academic authority, the court held that the parties’ failure to attempt good faith settlement discussions for the requisite timeframe, and in fact all issues relating to prematurity or ‘ripeness’ of claims under a tiered arbitration agreement, were points of admissibility.
The court therefore summarised its findings in Sierra Leone v SL Mining as follows
In its decision, the court endorsed Sierra Leone, finding that “if reaching the end of the settlement period is to be viewed as a condition precedent at all…it could only be a matter of procedure, that is, a question of admissibility of the claim, and not a matter of jurisdiction”. The court came to the same view that issues of admissibility were ‘case management decisions’ for the tribunal, and not issues which call into question its jurisdictional footing.
The Hong Kong Court of Appeal’s decision in C v D expressly endorses the English decisions in Sierra Leone and NWA v NVF, as well as similar judgments issued in other common law jurisdictions such as Singapore and New South Wales.
By way of brief context, in C v D, a dispute arose between a satellite owner in Hong Kong (C) and a Thai satellite operator (D) in relation to D’s entitlement to transmit video content into China and C’s efforts to switch off the satellite’s transponders. In the event of a dispute, the relevant provisions required the parties to “attempt in good faith promptly to resolve such dispute by negotiation”, permitting either party to refer the dispute to each party’s Chief Executive Officers for resolution at a meeting to be arranged within 10 business days of any such referral.
Neither party observed these provisions and, on 18 April 2019, D issued a notice of arbitration, to which C responded by asserting that the tribunal did not have jurisdiction because the parties had not complied with the pre-conditions to arbitration. Ultimately, the tribunal issued a partial award finding in D’s favour and dismissing C’s jurisdiction objection on the basis that D had in any event satisfied the requirement to attempt in good faith to resolve the dispute by negotiation. C then made an application for the partial award to be set aside under Section 81 of the Arbitration Ordinance (Cap 609), which imports Article 32 of the UNCITRAL Model Law wholesale, contending that the tribunal lacked jurisdiction.
The principal question before the court was whether compliance with pre-arbitration steps was a question of jurisdiction or admissibility. The court found that there was broad international consensus for the view that “non-compliance with procedural pre-arbitration conditions such as a requirement to engage in prior negotiations goes to admissibility of the claim rather than the tribunal’s jurisdiction”. Moreover, the court held that whether pre-arbitration procedural requirements have been fulfilled is a question that is “intrinsically suitable for determination by an arbitral tribunal”.
The court also emphasised that the question is fundamentally a point of construction, that is to say, whether the parties intended for disputes relating to the fulfilment of pre-arbitration procedural requirements to be a matter capable of reference to arbitration. Although there is a presumption that parties to an arbitration agreement intend any dispute arising out of their relationship to be decided by one tribunal, it is possible for parties to rebut that presumption with clear and unequivocal language, providing that satisfaction of pre-arbitration requirements is a strict condition precedent, absent compliance with which the tribunal will lack jurisdiction (although it is unclear why any party would choose to take this approach because it paves the way for expensive satellite litigation).
The Hong Kong Court of Appeal’s decision in C v D follows a recent trend in common law jurisdictions such as England & Wales and Singapore, now finally catching up to civil law jurisdictions like France and Switzerland, by confirming the difference between jurisdiction and admissibility.
However, accepting there is a distinction is one thing; clearly drawing the dividing line is quite another. It is not always obvious on which side of the line an issue falls. In his 2010 article, Jurisdiction and Admissibility, Jan Paulsson memorably compared the problem to trying to perceive the divide between night and day in twilight. Mr Paulsson’s recommended approach, his ‘lodestar’, was to try to identify whether the objecting party was taking aim at the tribunal, in which case it was likely an issue of jurisdiction, or at a particular claim, in which case it was likely an issue of admissibility. In C v D, the court described this approach as the “tribunal versus claim” test, and applied it to the arguments when determining that the objection was a question of admissibility.
A further question that often arises is what law should govern questions of admissibility. Questions of jurisdiction are typically addressed by reference to the law of the arbitral seat. So, until the decisions discussed above clarified the distinction between jurisdiction and admissibility, issues of admissibility were addressed in the same way. However, following the UK Supreme Court’s decision in Enka Insaat Ve Sanayi A S v OOO Insurance Company Chubb [2020] UKSC 38, it is now settled under English law that “the law which determines the validity and scope of the arbitration agreement will determine the validity and scope of the whole dispute resolution agreement”. Issues of admissibility will therefore be determined by the law governing the arbitration agreement which may of course differ from the law of the seat and the law governing the rest of the agreement.
The position is now clear that virtually all procedural conditions to arbitration (for example, good faith negotiation obligations, time-bar clauses, mandatory ADR provision and expert determinations prior to arbitration) are questions of bars to admissibility. And, if a bar to admissibility, it is an issue that the tribunal is alone empowered to decide. The tribunal may or may not decide the stay the arbitration pending compliance with the procedural condition – perhaps the usual course, given most pre-conditions are tied to a fixed time period – but it is its decision and not one that is potentially subject to judicial scrutiny.
Publication
In the rural village of Gwanda, Zimbabwe, a mother walks several kilometres each day to find firewood so she can cook for her children.
Publication
Southern Africa is a key focus of attention at the present time, as it faces a perfect storm of an energy emergency due to hydropower generation being severely impacted by reduced water levels due to droughts whilst the demand of its regional miners for clean baseload power rapidly accelerates.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025