Publication
This year’s Africa Energy Forum presents a unique opportunity for African collaboration
In the rural village of Gwanda, Zimbabwe, a mother walks several kilometres each day to find firewood so she can cook for her children.
Australia | Publication | June 2025
The Victorian Government has introduced significant changes to the Domestic Building Contracts Act 1995 (Vic) (DBC Act), affecting contract rules, builder obligations and consumer protections.
This is welcome reform to modernise the DBC Act and make it more workable. Perhaps most importantly, the Bill removes many of the consumer protection provisions in the DBC Act for contracts between developers and builders. Below, we summarise the proposed reforms which are most significant for developers and builders.
If the Bill passes, most reforms will commence on 1 December 2026, unless proclaimed earlier, to allow time for industry preparation.
The Bill is the second major package of building reforms introduced recently in Victoria, following on from the Building Legislation Amendment (Buyer Protections) Act 2025 (Vic), which we wrote about here and here. That Act received a mixed reaction from industry groups, whereas initial industry reaction to this Bill has been positive.
The Bill introduces a new definition of “developer” and provides that only certain provisions of the DBC Act will apply to contracts between builders and developers. These include implied warranties, registration requirements, requirement for the builder to obtain information about foundations, and a new short list of contract content requirements (4 requirements instead of the current 21).
Many other requirements will fall away, including limits on deposits, restrictions on cost plus contracts and cost escalation clauses, banning of arbitration clauses, regulation of provisional sums and prime cost items, requirement for a contract information statement, the extensive list of contract content requirements, requirements for price change warnings, delay allowances, cooling off periods, regulation of variations and limits on progress payments.
These changes reflect the reality that contracts between sophisticated developers and builders do not require regulation by consumer protection provisions.
The DBC Act will no longer apply to the preparation of plans, specifications and bills of quantities for the carrying out of domestic building work. Industry is also likely to welcome this change, enabling design work to be carried out without the constraints of the DBC Act requirements.
The requirements for cost escalation clauses will be reformed, to allow cost escalation clauses in domestic building contracts with a contract price of $1 million or more.
There will still be strict regulation of cost escalation clauses; they will be void if not in the prescribed form and signed or initialled by the building owner, and there will be a 5 per cent ceiling on price increases from cost escalation clauses.
The provisions regulating variation of plans and specifications in major domestic building contracts will be replaced with a more practical regime. The current regime is prescriptive and complex, with different requirements depending on which party is seeking the variation.
This will be replaced by a single variation process that applies whether the variation was requested by the builder or the building owner. The parties must agree in writing to vary the plans or specifications, with the agreement to comply with certain requirements and to be signed by both parties. Some exceptions to the requirement are also provided for building surveyor required variations and urgent variations.
The provisions permitting a building owner to end a major domestic building contract if the completion time or cost blows out will be amended to remove the requirement that the reason for the increase in time or price must be a reason the builder could not have reasonably foreseen at the contract date. The purpose of the change is to simplify the termination process so the owner does not need to make an assessment about the builder’s state of mind and what might or might not have been reasonably foreseeable.
The building owner will be entitled to end the contract if the contract price rises by 15 per cent or more, or completion time blows out by 50 per cent (excluding increases arising from prime cost items, provisional sums and variations initiated by the building owner). These thresholds are unchanged from the current DBC Act.
The Bill provides for the limits on deposits and progress payments that a builder can claim to be moved from the DBC Act into regulations; this will enable them to be updated more easily. The Bill lays the groundwork for different percentage limits to be prescribed for progress payments for major domestic building contracts to build a home, depending on what percentage of the cost is attributed to the use of prescribed modern methods of construction. We will need to await release of the regulations to know exactly what is planned.
There will also be a general proportionality requirement that applies to all major domestic building contracts (including renovations), prohibiting builders from claiming an amount that does not relate directly to the progress of the building work.
The above changes will only apply in relation to contracts entered into on or after commencement of the reforms. This will help to make the transition smooth for industry, providing certainty about when to begin using updated forms of domestic building contracts.
The reforms in the Bill are likely to be welcomed by industry. In the lead up to commencement of the reforms builders and developers will need to update contract templates and procedures and consult with the Victorian Government in relation to the content of proposed regulations.
We will monitor the progress of the reforms and provide an update if the Bill passes. Please contact us should you wish to discuss the impacts for your business or projects.
Publication
In the rural village of Gwanda, Zimbabwe, a mother walks several kilometres each day to find firewood so she can cook for her children.
Publication
Southern Africa is a key focus of attention at the present time, as it faces a perfect storm of an energy emergency due to hydropower generation being severely impacted by reduced water levels due to droughts whilst the demand of its regional miners for clean baseload power rapidly accelerates.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025