COVID-19 is having far reaching impacts on the construction industry’s supply chains, cash flows and workforces. The pace of change is so rapid (this briefing was last updated on June 10, 2020) that developers and construction participants across the supply chain need to make sure they are on top of the provisions of their construction contracts, health and safety policies and employment law practices, all with the additional pressure of protecting their workers from exposure to COVID-19.

This page provides links to official guidance and information, as well as to our experienced legal professionals who can support you in weathering the storm.

Built environment, transport, energy and infrastructure

The UK Government recently published its COVID-19 recovery strategy. Amongst other things, the strategy encourages workers in the construction industry in England to travel to work if their construction site is open and they cannot work from home. Where adherence to social distancing measures is not practicable on site, employers should implement the measures set out in the fourth COVID-19 construction Site Operating Procedures (SOP), published on May 19, 2020.

However, official advice in Northern Ireland, Scotland and Wales differs. The Scottish Government, for example, is only now encouraging the construction sector to begin planning and pre-start site preparations, with a goal of introducing a ‘soft re-start’ to operations in the future. The Scottish First Minister has made clear that work on construction sites should remain closed, unless the work is for essential projects. Essential projects include those which are critical to the national response to COVID-19, for example creating or repurposing facilities for treatment, research or testing. The guidance also permits essential and time-critical maintenance and repair projects in certain sectors, including energy, communications and transport.

Government advice on minimising transmission

The Government has published workplace safety guides covering eight workplace settings which are allowed to open under the new COVID-19 recovery strategy, including construction sites. A summary of the key points can be found here.

The SOP and the Government’s construction-specific guidance (the Construction Workplace Safety Guidance) outline the following additional measures that employers should take:

  1. Introducing one-way flow-through areas and floor markings to maintain social distancing (where possible). Minimising the number of unnecessary visits to the worksite. Where site visits are required, making sure customers, visitors and contractors understand how to maintain safety.
  2. Maintaining social distancing and avoid surface transmission when goods enter and leave the site.
  3. Sharing the results of risk assessments with the workforce.
  4. Ensuring workers who have symptoms or who live with others who have symptoms stay at home and are tested under the Government’s test and trace service.

The most recent iteration of the SOP removes the requirement to keep face-to-face contact to 15 minutes or less. It also states that workplaces should not encourage the precautionary use of extra PPE to protect against COVID-19. Similarly, the Construction Workplace Safety Guidance notes PPE’s ‘extremely limited’ role in providing additional protection against COVID-19, but indicates that employers should provide PPE to workers if a risk assessment shows it is required and should support workers to use face coverings should they choose to wear one. 

Both employers and contractors (in their dealings with their sub-contractors) should also be looking at what alternative site arrangements can be put into place to ameliorate the position. Possible steps include varying shift patterns (to minimise the numbers of workers on site and also, particularly in London and metropolitan areas, to enable workers to commute off-peak), changing works programmes with a view to preventing trades working too close to each other and altering the location of rest areas. 

The Construction Leadership Council has provided a template letter which contractors can amend and issue to their workers to show that their travel to site is essential. All changes to site practices should be documented and effected in accordance with the contractual arrangements between the parties.

Onshore wind-specific considerations

The onshore wind industry plays a key role in the provision of electricity in the UK. Safety On and Renewable UK have published guidance on site operations and activities during COVID-19 for onshore wind sites (the Onshore Wind Guidance).

In addition to the SOP and the Government’s Construction Workplace Safety Guidance, the Onshore Wind Guidance suggests specific health and safety measures that can be taken at turbines and substations and when operating service lifts and ladders. Amongst other things, the Onshore Wind Guidance encourages site managers to keep a log of all turbines being worked on and details of who has worked on them, should a team member develop COVID-19 symptoms.

Key H&S issues

The Government has confirmed that the UK has passed the first peak of COVID-19 infections. Under its COVID-19 recovery strategy, the Government confirmed that lockdown restrictions will only be eased if it is confident that doing so would not risk a second peak of infections.

The SOP states that the health and safety requirements of any construction activity must not be compromised and that if an activity cannot be undertaken safely, it should not take place. The SOP obligations are in addition to the Section 2 and 3 obligations under the Health and Safety at Work, etc. Act 1974, where every employer owes a duty of care, as far as reasonably practicable, to provide a safe place and system of work for their employees and any person in relation to their activities.

In order to keep working operators of construction sites will need to consider some of the following in the short- to medium- term:

  1. Travel arrangements and continuity for site work forces
  2. Materials supply and delivery
  3. Safe site operations and equipment
  4. Waste material collection and disposal
  5. Site safety risk management and audit trail
  6. Cash flow implications and debt financing
  7. Contractual penalties for delay and force majeure conditions
  8. Crisis management and incident response planning

We have a team of knowledgeable lawyers from a variety of disciplines who can support you on a 24/7 basis with these issues.



Contacts

Head of Environment, health and safety, Europe, Middle East and Asia; Partner

Recent publications

Subscribe and stay up to date with the latest legal news, information and events...