Australia: Construction force majeure and alternative relief
Force majeure and alternative relief under standard form construction contracts and local law.
Global | Publication | May 2020
In these extraordinary times, our market-leading, global construction team is increasingly advising on force majeure and related relief claims arising under the various different standard forms of construction contract, which are themselves subject to a variety of different governing laws.
To assist navigating such claims, in particular for international organisations with construction projects in multiple jurisdictions, we have prepared this concise reference guide, which sets out the relevant provisions of the standard form construction contracts used in - and the local laws of - the countries listed below.
We shall be updating this guide periodically, so do let us know if there are countries and/or standard form contracts that you would like to see included.
Our global construction team advises throughout the lifecycle of a construction project, from procurement structuring, tendering, contract drafting and negotiation, through to strategic advice during construction, operation and maintenance and on resolving construction related disputes. Our clients include governments, lenders, project companies/sponsors, developers, contractors, consultants and institutional investors. We combine sector knowledge with commercial focus to deliver timely and reasoned construction law advice.
Publication
Force majeure and alternative relief under standard form construction contracts and local law.
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law.
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
The Japanese government passed the Hydrogen Society Promotion Act (the Hydrogen Act) on 17 May 2024, which implements a ‘twin-track’ approach to subsidising the hydrogen economy
Publication
As the world embraces the ideals of sustainability and works towards reduced reliance on fossil fuel sources of energy and reduction in greenhouse gas emissions, Singapore has set out how it plans to cut emissions to meet its 2030 Nationally Determined Contribution climate targets – with carbon capture technology expected to be among the most effective measures.
Publication
Singapore launched its National Hydrogen Strategy on 25 October 2022. The Singapore government believes that low-carbon hydrogen has the potential to be a major decarbonisation pathway to support Singapore’s accelerated transition towards net zero by 2050, while strengthening its energy security and resilience. It foresees low-carbon hydrogen playing an important role in: