We use cookies and other similar technology to collect data about you to allow us to deliver our online services, measure our website audience and improve your browsing experience. Full details on the cookies we use are set out in our Cookies policy. Please click OK to signify your consent to our use of cookies.
You can withdraw your consent by clicking “manage cookies” and following the instructions shown.
Global | Publication | November 2016
On June 9, 2016, the Quebec government tabled Bill 108, the Act to facilitate oversight of public bodies’ contracts and to establish the Autorité des marchés publics (Bill). This Bill builds on the legislative and regulatory changes that were introduced further to the passage of the Integrity in Public Contracts Act in December 2012.
The Bill proposes the establishment of a body called the Autorité des marchés publics (AMP) that would be empowered, among other things, to monitor and intervene in tendering and awarding processes for public contracts.
The AMP will be a mandatary of the State and have the following mission and functions:
Under the proposed complaint examination process, any interested person (complainant) may file a complaint with the AMP when the tender documents:
To avail itself of the complaint examination process, the complainant must first have complained to the public body involved. If the complainant is not satisfied with the public body’s decision or the public body does not respond to the complaint within the prescribed time periods, the complainant may file a complaint with the AMP before the expiry of the time periods specified for that purpose, in accordance with the prescribed procedure. A complaint may also be filed directly with the AMP, without it having to first be filed with the public body, if the complainant is informed of an amendment made to the tender documents during the period starting two days before the complaint filing deadline indicated on the electronic filing system; in this case, certain deadlines will have to be met.
The AMP may, on summary examination, dismiss any complaint that it considers abusive, frivolous or clearly unfounded.
If it considers the complaint admissible, the AMP informs the public body, which must then, without delay, submit its observations to the AMP and, as applicable, send the AMP a copy of the reasons for its decision.
The AMP has 10 days from the time it receives the public body’s observations to make a decision with reasons in writing. If the complaint cannot be processed within that time, the AMP must agree with the public body on an additional time period. If the AMP and the public body cannot agree on an additional time period, the AMP will have only an additional five-day time period to make its decision. If the AMP fails to make a decision within that time, it will be deemed to have decided that the tendering process complies with the normative framework.
During the examination of a complaint, the AMP must, if need be, defer the submission of bids until a new tendering closing date is set by the public body in accordance with the decision that the AMP will make regarding the complaint. If the process is an awarding process, not a tendering process, the AMP must, if need be, defer the projected contract date.
After it completes its investigation, the AMP may order the public body to amend its tender documents or cancel the public call for tenders. Clearly, this is an important power devolved to the AMP.
Moreover, any public contract entered into after a tendering or awarding process and before the AMP has made a decision on a complaint sent to it will be cancelled by operation of law, as will any public contract entered into in contravention of an order made by the AMP.
Businesses will now have a new, inexpensive avenue by which to rebalance the scales between them and their competitors before it’s too late. However, they will have to act expeditiously and comply with the specified terms and conditions. They will also have to refrain from taking legal action before the AMP has made a decision, or else their complaint will be dismissed.
In view of the powers given to the AMP and the substantial benefits promised by the new system, it is both likely and desirable that businesses will not hesitate to use the new oversight mechanism. It will be up to the AMP to put the necessary protections in place to minimize the risk of the rules being used by some tenderers for dilatory or other strategic purposes.
Publication
The collapse of Silicon Valley Bank, Signature Bank and Silvergate Bank in the last week has caused turmoil in global financial market.
Publication
The European Union’s Foreign Subsidies Regulation (the FSR) entered into force on 12 January 2023 and creates a new regime aimed at combating distortions of competition on the EU internal market caused by foreign subsidies. It imposes mandatory notification and approval requirements for acquisitions of significant EU businesses and large EU public tenders, and gives the European Commission (EC) extensive powers to launch ex officio investigations. The notification requirements go live on 12 October 2023.
Subscribe and stay up to date with the latest legal news, information and events...
© Norton Rose Fulbright LLP 2023