Implementation tracker

The Pension Schemes Act 2026 received Royal Assent on April 29, 2026.

This tracker sets out the key provisions of the Act for the private sector and the related regulations, consultations and guidance for each area. We will keep this updated so it remains a single reference point as implementation progresses.

If you would like to explore any point in more detail, or discuss anything related to the Act, whether or not it’s noted in the tracker, please contact the Norton Rose Fulbright Pension team who will be happy to assist.

Defined benefit provisions

What is it? Status Find out more
Return of surplus Trustee power to amend scheme rules to allow payment of surplus.

✖ Not in force. Regime is expected to apply from spring 2027.

Direct surplus payments to members are expected to become authorised payments from April 6, 2027.

Regulations expected to be in force by spring 2027.

Consultation on the draft regulations published on June 10, 2026, and closed on September 2, 2026.

The Pensions Regulator (TPR) guidance on surplus distributions is expected to be consulted on in late autumn 2026 and published by April 2027.

Consultation on the draft legislation to create a new member surplus payment was published on July 13, 2026 and closed on September 7, 2026. The legislation is expected to be included in the Finance Bill 2026-2027.

Financial Reporting Council technical actuarial guidance to help scheme actuaries certify that surplus payments to employers meet the legislative requirements is expected to come into force in April 2027. The FRC held a roundtable to discuss the guidance on July 28, 2026.

Webinar: discussing the potential for companies of ongoing DB schemes to share in surpluses and the conditions that are likely to apply (September 2025).

Podcast: future of DB surplus (September 2025).

Brief guide on the key points on return of surplus.

TPR has published its early views setting out factors trustees should take into account (June 2026).

Consultation on the draft legislation to create a new member surplus payment (July 2026).

Superfunds Introduces a statutory framework for commercial DB superfunds.

✖ Not in force. Regime is expected to apply from the second half of 2028.

Regulations expected to be in force in the second half of 2028.

Consultation on the regulations is expected in the first half of 2027.

TPR code: consultation on the draft code expected in the first half of 2028. The final code is expected in the second half of 2028.

Brief guide on the key points on superfunds.

TPR’s current superfund guidance.

Virgin Media fix A statutory fix for amendments made to contracted out defined benefit schemes between 1997 and 2016 where written actuarial confirmation was required but cannot now be shown. Where a scheme cannot show that actuarial confirmation was obtained, it may seek a retrospective actuarial confirmation. ✔ In force. Came into force on April 29, 2026.

Checklist of things trustees should be doing now to get ahead (April 2026).

Briefing on the FRC guidance for actuaries providing a retrospective confirmation (February 2026). The FRC issued their final form guidance in May 2026.

Digest of the Virgin Media decision (August 2023).

Update

on the

Virgin Media

fix and the fact schemes with proceedings issued.

on or before June 5, 2025, cannot use the statutory fix (March 2026).

TPR guidance urges trustees to start taking action now (March 2026).

Brief

guide

on the key points on

Virgin Media

fix.

Defined contribution provisions

What is it? Status Find out more
Value for money Creates a new value for money framework for trust-based DC schemes. The new framework will mirror the framework for contract-based schemes being issued by the Financial Conduct Authority (FCA), which is still being finalised.

✖ Not in force. Regime is expected to apply from 2028 for master trusts and group personal pension plans and from 2029 for all other in-scope schemes.

Regulations expected by January 2027.

Consultation on TPR/FCA policy, the draft regulations and draft FCA rules closed on September 15, 2026. A response is expected by January 2027.

TPR code expected in the first half of 2028. TPR expects to consult on this in 2027.

TPR guidance. TPR materials on the proposed framework and technical overview published in August 2026. Further TPR guidance expected as the implementation of the value for money framework progresses.

FCA policy statement expected in the first quarter of 2027.

Brief guide on the key points on value for money.

Detailed briefing on value for money framework (September 2026).

Value for money framework: TPR’s response to consultation, further consultation and discussion paper (July 2026).

Value for money consultation and the accompanying draft regulations and FCA rules (July 2026).

TPR overview of the value for money framework for trust-based schemes (August 2026).

TPR technical overview of the value for money framework (August 2026).

DC megafunds – scale requirements All multi-employer master trusts and group personal pension providers used for automatic enrolment must have at least £25 billion of assets under management in a ‘main scale default arrangement’ by 2030.

✖ Not in force. Regime is not expected to apply before January 1, 2030.

Regulations will not be in force before January 1, 2030.

Consultation on the regulations expected in late 2027. Final regulations expected in the first half of 2029.

TPR code of practice:consultation expected in mid 2028. Final code of practice expected in the first half of 2029.

Brief guide on the key points on DC megafunds.

Detailed briefing on scale requirements (September 2026).

Department for Work and Pensions (DWP) policy and accompanying TPR statement on scale measures (July 2026).

Mandation power (Mansion House Accord) Allows the government to require that a scheme’s main default fund assets are invested in specified asset classes, subject to certain conditions being satisfied.

✖ Not in force. The power cannot be exercised before January 1, 2028.

Regulations expected but it is unclear when.

Consultation on the regulations is expected but it is unclear when.

Blog: balancing growth and governance with the Mansion House Accord. (January 2026).

Blog: The Mansion House Agenda: a legislative turning point (May 2026)

Brief guide on the key points on the mandation power.

Bulk transfer without consent Contract-based DC schemes may bulk transfer their members’ pots to another scheme without member consent.

✖ Not in force. Regime is expected to apply from early 2028.

Regulations expected to be in force by early 2028.

Consultation on the regulations is expected between January and March 2027.

FCA rules expected after the regulations are agreed. FCA will consult on the rules.

Brief guide on the key points on bulk transfers without consent.
Default retirement pathways (guided retirement) Must offer members of DC occupational schemes a default option which will provide retirement income.

✖ Not in force. Regime is expected to apply to master trusts at some point in 2029, and to other DC occupational schemes from 2030.

Regulations expected to be in force by the second half of 2028.

Consultation on the regulations is expected in the second half of 2027.

DWP policy paper setting out the guiding principles for default pension solutions published on July 13, 2026. Final policy paper expected in the first half of 2028.

TPR guidance: consultation expected in the middle of 2028. Final guidance expected in the second half of 2028.

FRC standards for illustrations of common decumulation standards expected in the second half of 2028.

Brief guide on the key points on default retirement pathways.

Detailed briefing on guided retirement (September 2026).

Policy paper on Guided Retirement Guiding Principles (13 July 2026).

PASA Guided Retirement Operational Readiness Guidance (September 2026).

Small pots consolidation Automatic consolidation for certain dormant DC pots worth £1,000 or less into a consolidator scheme.

✖ Not in force. Consolidation is expected to start in 2030.

Tranche 1 regulations (building the foundations for consolidation): consultation published September 15, 2026 and closes on November 17, 2026. Response to this consultation and draft regulations for consultation are expected in the first half of 2027. The regulations are expected to be in force in the first half of 2028.

Tranche 2 regulations (further consolidation considerations): consultation is expected between the second half of 2027 and very early 2028. Responses to this consultation and draft regulations are expected in the summer of 2028. The regulations are expected to be in force in the first half of 2029.

TPR code / FCA rules – consultation on both expected in the middle of 2027 with the final code expected in the second half of 2028. The FCA policy statement is expected in the first half of 2028.

The first applications for consolidator schemes are expected to be made at the end of 2028 with the consolidator schemes selected in early 2029.

Brief guide on the key points on small pots consolidation.

Consultation: Small Pots: A pathway for consolidation (September 2026).

Contact