Australia: Construction force majeure and alternative relief
Force majeure and alternative relief under standard form construction contracts and local law.
Global | Publication | May 2020
In these extraordinary times, our market-leading, global construction team is increasingly advising on force majeure and related relief claims arising under the various different standard forms of construction contract, which are themselves subject to a variety of different governing laws.
To assist navigating such claims, in particular for international organisations with construction projects in multiple jurisdictions, we have prepared this concise reference guide, which sets out the relevant provisions of the standard form construction contracts used in - and the local laws of - the countries listed below.
We shall be updating this guide periodically, so do let us know if there are countries and/or standard form contracts that you would like to see included.
Our global construction team advises throughout the lifecycle of a construction project, from procurement structuring, tendering, contract drafting and negotiation, through to strategic advice during construction, operation and maintenance and on resolving construction related disputes. Our clients include governments, lenders, project companies/sponsors, developers, contractors, consultants and institutional investors. We combine sector knowledge with commercial focus to deliver timely and reasoned construction law advice.

Publication
Force majeure and alternative relief under standard form construction contracts and local law.

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law.

Publication
Force majeure and alternative relief under standard form construction contracts and local law

Publication
Force majeure and alternative relief under standard form construction contracts and local law
Publication
21 airlines (the Airlines) have committed to change their practices on environmental claims and statements that were considered misleading by the Consumer Protection Cooperation (CPC).
Publication
For the sustainable aviation fuel (SAF) industry, the key initiative to emerge from COP30 was the “Belém 4x Pledge”, spearheaded by Italy, Japan, India and Brazil and supported by 23 other countries, to quadruple sustainable fuel production and use by 2035. The pledge focused on the need to take comprehensive domestic action to support sustainable fuel development and strengthen international collaboration, whilst ensuring that efforts to scale-up production are conducted in an environmentally and socially responsible manner.
Publication
In King Crude Carriers SA & Ors v Ridgebury November LLC & Ors [2025] UKSC 39, the Supreme Court overturned the Court of Appeal and held that the claimant sellers (the Sellers) were not entitled to claim the deposits promised under sale contracts as a debt