
Publication
Essential Corporate News – Week ending 11 July 2025
On 1 July 2025, the Quoted Companies Alliance (QCA) published three new board committee guides to accompany the QCA Environmental and Social Guide published in December 2024.
Global | Publication | December 18, 2018
On 17 December 2018 a new security of payment regime took effect in Queensland.
Newly commenced provisions in the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) have replaced the Building and Construction Industry Payments Act 2004 (Qld) (BCIP Act) and Subcontractors’ Charges Act 1974 (Qld), introducing a number of key changes.
A claimant is not required to state on a payment claim that it is made under the BIF Act.
Any written document, including a letter or an email, is capable of being a valid payment claim under the BIF Act and should be treated as such if it:
A payment schedule must be issued within 15 business days after the payment claim is given, or earlier if a shorter period is stated in the construction contract.2 This applies to both standard payment claims and complex payment claims regardless of the reference date.3
Respondents are no longer permitted to include in the adjudication response new reasons for withholding payment that were not originally ‘stated’ in the payment schedule.4 This applies even if the adjudication is for a complex payment claim.5
Accordingly, respondents should ensure that payment schedules are prepared with the new regime in mind, setting out full and complete reasons for withholding payment.
Under the BCIP Act, if a respondent failed to issue a payment schedule, a claimant was required to give the respondent a ‘second chance’ notice before applying for judgment or adjudication.6 Under the new regime, if a respondent fails to pay the amount owed to the claimant in full by the due date, the claimant is not required to provide a ‘second chance’ notice before proceeding to adjudication. However, a ‘warning notice’ will need to provided to the respondent if the claimant intends to commence court proceedings to recover an unpaid amount owed to the claimant.7
If the construction contract does not provide for a reference date after termination, a further reference date is now deemed to arise on the date of termination.8
Claimants now have one last opportunity to access adjudication following termination.
If an adjudicator decides that a respondent is required to pay an adjudicated amount, the adjudicated amount must be paid within 5 business days of the adjudicator’s decision, unless a later date is determined by the adjudicator in accordance with the BIF Act.9
The consequences for a respondent that fails to comply with the provisions of this new regime may be significant. For example, failing to provide a payment schedule in time will result in deemed liability for the full amount claimed.
New disciplinary measures have been introduced, with the imposition of statutory penalties and prosecution by the QBCC in circumstances such as when a respondent fails to pay an adjudicated amount in time.
BIF Act s 68.
BIF Act s 76(1).
Under s 18(3) of the BCIP Act, a respondent had 30 business days to issue a payment schedule for complex payment claims served more than 90 days after the reference date.
BIF Act s 82(4).
BIF Act s 24(5).
BCIP Act s 20A(2).
BIF Act s 99(2).
BIF Act s 67(2).
BIF Act s 90.
Publication
On 1 July 2025, the Quoted Companies Alliance (QCA) published three new board committee guides to accompany the QCA Environmental and Social Guide published in December 2024.
Publication
In the two years since our last climate litigation update, the prevalence and variety of global climate litigation around the world has continued to increase.
Publication
Selon un rapport conjoint du Bureau du surintendant des institutions financières (BSIF) et de l’Agence de la consommation en matière financière du Canada (ACFC), environ 70 % des institutions financières fédérales prévoient utiliser l’IA d’ici 2026 .
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025