In DKB v DKC [2025] SGHC(I) 11, the Singapore International Commercial Court (SICC) granted a conditional stay of enforcement of an award, holding that a dispute over whether a post-award settlement agreement precluded enforcement fell within scope of that agreement's arbitration clause and had to be resolved through arbitration before continuing enforcement proceedings. In a related judgment, DKB v DKC [2025] SGHC(I) 14, the SICC found the respondent did not comply with the condition of the stay to commence arbitration within a deadline but granted the respondent additional time to commence.
The Singapore International Commercial Court (SICC) has issued two related judgments involving a dispute over the enforcement of an arbitral award.
The case involved the assignment of an award arising from a Swiss-seated arbitration by the successful party to DKB under the terms of a stay and settlement deed (Settlement Deed). Under the Settlement Deed, DKC, as the losing party, agreed to pay DKB a sum of money over several instalments to satisfy the award, while DKB agreed in return to stay enforcement of the award. The Settlement Deed contained an arbitration clause providing for disputes to be settled in accordance with the Expedited Arbitration Rules of the SCC Arbitration Institute.
DKC allegedly failed to comply with its payment obligations under the Settlement Deed, and DKB responded by filing an application in the SICC to enforce the award pursuant to section 29 of Singapore's International Arbitration Act 1994 (IAA 1994).
DKC resisted enforcement, arguing that US sanctions prevented it from making lawful payments and that the dispute regarding its payment obligations must be arbitrated in Stockholm under the Settlement Deed's arbitration clause. In the first decision, the SICC found that:
Therefore, the SICC ordered a stay of enforcement but made it conditional on DKC commencing an expedited arbitration within ten days of its order and to diligently prosecute it. No security was required from DKC, given the anticipated expedited resolution. In the second decision, the SICC noted that DKC did not comply with the ten-day deadline to commence arbitration in Stockholm and remarked that this was without any real justification. However, having regard to the quantum of the claim, the parties' agreement to arbitrate their dispute and the limited prejudice against DKB, the SICC granted DKC additional time to commence.
These important decisions highlight the need to draft settlement clauses carefully, ensuring clarity on how breaches can affect rights to enforce awards. Further, consideration should be given to explicitly addressing potential sanction risks or force majeure events.
Cases: DKB v DKC [2025] SGHC(I) 11 (16 April 2025); DKB v DKC [2025] SGHC(I) 14 (2 May 2025) (Thomas Bathurst IJ).
Publication
The Internal Regulations of the National Energy Commission or “CNE” were published in the Federal Official Gazette.
Publication
The Regulator’s annual funding statement for private sector DB schemes was published on April 29, 2025. It is the first such statement since the new DB funding regime came into force from September 22, 2024, onwards.
Publication
The destruction of the 46,000-year-old Juukan Gorge rock shelters in 2020 was a wakeup call for project proponents on the importance of successfully managing Aboriginal and Torres Strait Islander cultural heritage risks.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025