
Publication
Essential Corporate News – Week ending 11 July 2025
On 1 July 2025, the Quoted Companies Alliance (QCA) published three new board committee guides to accompany the QCA Environmental and Social Guide published in December 2024.
Global | Publication | February 7, 2018
On February 2, 2018, the Mexican Ministry of Energy (“SENER”) issued the bidding guidelines for the first international public bid for electric transmission lines.
The project consists in the interconnection of the isolated Electric System of Baja California (“BC”) with the National Interconnected Electric System (“SIN”) through the construction of two converter stations and a high voltage direct current transmission line, with an estimated length 1,400 kilometers circuit at a voltage level of ± 500 kV and a transmission capacity of 1,500 MW (“Project”).
For the implementation of the Project, SENER will use a public-private participation model known as DFBOT (Design, Finance, Build, Operate and Transfer).
The term of the contract will be 30 years, counted from its execution. At the end of the term all the assets will be transferred to the Mexican State.
The minimum percentage of Local Content (Contenido Nacional) that must be met by the winning bidder will be 30% of the total value of the construction phase of the Project.
Any interested applicant must meet the requirements set in the registration and prequalification stage of the bid. Most relevant requirements relate to financial capability and experience of the participants. For example:
The participants must provide a bid guarantee (garantia de seriedad) effective for a term of 180 days in the amount of MX$462.5 million.
The bidding guidelines provide for the incorporation of a private trust, where the contractor will be settlor and the Mexican State will be the beneficiary. All assets, income and obligations of the project and the contractor will be contributed to the trust.
The winner of the tender will be the bidder requesting the lowest constant annual contractual payment (“CACP”). The Energy Regulatory Commission (“CRE”) will include the CACP in the electricity transmission tariff and the National Center for Energy Control (“CENACE”) will pay directly to the contractor, with the resources derived from the transmission rate.
The contractor assumes all the risks of the Project in the stage prior to its commercial operation date.
The contractor shall have the obligation to obtain the rights of way necessary for the development of the Project. The construction phase will commence only until all of the rights of way have been secured.
Publication
On 1 July 2025, the Quoted Companies Alliance (QCA) published three new board committee guides to accompany the QCA Environmental and Social Guide published in December 2024.
Publication
In the two years since our last climate litigation update, the prevalence and variety of global climate litigation around the world has continued to increase.
Publication
Selon un rapport conjoint du Bureau du surintendant des institutions financières (BSIF) et de l’Agence de la consommation en matière financière du Canada (ACFC), environ 70 % des institutions financières fédérales prévoient utiliser l’IA d’ici 2026 .
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025