
Publication
International Restructuring Newswire
Welcome to the Q2 2025 edition of the Norton Rose Fulbright International Restructuring Newswire.
United Kingdom | Publication | August 2023
The pension scheme was amended in 1999 and no actuarial confirmation that it continued to comply with contracting-out requirements could be found.
The amendment was for pension earned for future service to have a lower rate of revaluation.
The case raised three issues relating to contracted-out rights:
The High Court decided in relation to contracted-out rights:
On July 20, 2023, Virgin Media was granted permission to lodge an appeal, but it could be many months before an appeal is heard.
The judgment confirms that rules related to contracted-out benefits cannot be altered without the statutory actuarial confirmation having been obtained and that non-compliant alterations are void.
The judgment impacts changes “relating to” section 9(2B) rights made between April 6, 1997, and April 5, 2013. Arguably it also applies, by extrapolation, to any changes to future service rights between April 6, 2013 (when the legislation was changed to require a certificate for changes to future services rights only) and April 5, 2016 (when salary-related contracting-out was abolished).
Section 9(2B) rights are benefits earned by members of salary-related contracted-out occupational pension schemes in respect of pensionable service between April 6, 1997 and April 5, 2016. Members’ benefits earned in this period must be at least as good as those provided by a reference scheme statutory standard (known as the “reference scheme test”).
While no actuarial confirmation was needed for administrative or other amendments “not” related to section 9(2B) rights, for example, changes to administration, the addition of trustee powers or to the scheme’s name, the judgment casts doubt on whether such changes would be valid, if the deed also made changes relating to section 9(2B) rights without the required actuarial confirmation.
Common practice has been for schemes to have discussed whether a certificate was required with the scheme actuary and concluded whether or not one was necessary ahead of making scheme changes. The judgment now potentially brings this practice into question, including changes made in good faith on the basis that no actuarial confirmation was required, for example where changes made between 1997 and 2013 impacted the future only (e.g. where the scheme was closed to future accrual, in which case the law required the scheme’s contracting-out certificate to be surrendered and therefore no past or future service rights were being affected by the closure to accrual) or where the contracted-out rights were not adversely impacted.
The judgement was also predicated on the basis that no actuarial certificate had in fact been provided in respect of the particular deeds referenced in the case. There was no commentary about what the position may be where a certificate may be referred to (for example in the recitals to the deed) but simply cannot be located.
It is hoped that the appeal will provide clarity on these important issues for schemes.
If the decision is not reversed (or clarified) on appeal, there is also a route for the DWP to promote regulations to allow retrospective actuarial confirmations that schemes would have continued to comply with the reference scheme test in relation to any historical deeds of amendment where there may be doubt as to whether the actuarial certification was provided at the relevant time.
In the meantime, what action, if any, should trustees and sponsoring employers take – especially schemes which are in the process of restructurings, particularly a total buy-in or buy-out?
For ongoing schemes, we think it makes sense for trustees and employers to await the outcome of the appeal before taking any steps to assess whether the case could impact on scheme’s liabilities.
For schemes approaching the end-game, it may depend on the views of the insurer or the employer’s willingness to provide indemnity protection, as to whether a wholesale review of historic deeds is required.
Whilst the decision (if not reversed or clarified), could result in further liabilities, a detailed review would be required, which would be expensive, take time and may ultimately prove unnecessary depending on the status of the appeal. It is also likely that a review would not give complete certainty as, as with most schemes, full records including contemporaneous actuarial advice may not exist. Further complications could exist for schemes with transferred in benefits or complex structures arising from historic mergers. A full review may simply be impossible.
We are continuing to follow any appeal of the judgment and can advise clients further if necessary.
Publication
Welcome to the Q2 2025 edition of the Norton Rose Fulbright International Restructuring Newswire.
Publication
In the current geopolitical climate, with the imposition of tariffs and associated macroeconomic uncertainty, publicly traded companies across sectors will need to consider the potential impact on their business in the context of their ongoing disclosure obligations.
Publication
In July 2022 the UK Secondary Capital Raising Review published its report (Report) setting out a series of bold and wide-ranging recommendations for improving the secondary capital raising regime in the UK designed to make it quicker, more flexible, more inclusive of retail investors and more cost-effective, as well as moving towards digitisation and making better use of technology.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025