The Polish government published draft renewable energy regulations in November 2016, setting the maximum volume and value of electricity to be auctioned, and the order of auctions to be held in 2017. The details are set out below.
Context
Renewable energy sources in Poland have been developing at an uneven pace, with most growth in the wind sector. The Polish government is now going to focus on technologies relying on biogas, biomass and hydropower, and on solar (PV) installations (seen as important to the security of Poland’s energy supply, especially during the summer months). Certain types of installation will not be allotted anything in 2017: no auctions will be held in these categories – this includes wind farms that are already in operation.
The law
The Renewable Energy Sources Act, 2015 (Journal of Laws 2015, 478)
Categories of auction baskets
Installations |
Maximum |
Maximum |
---|---|---|
Capacity utilisation rate >3,504 MWh/MW per year |
1,659,047 MWh |
PLN 556,174,673 |
Capacity utilisation rate >3,504 MWh/MW per year |
784,122 MWh |
PLN 337,458,778 |
Capacity utilisation rate >3,504 MWh/MW per year |
10,502,338 MWh |
PLN 3,768,589,370 |
Installations | Maximum volume | Maximum value |
---|---|---|
Capacity utilisation rate >3,504 MWh/MW per year |
825,000 MWh
|
PLN 308,182,262 |
Capacity utilisation rate >3,504 MWh/MW per year |
540,000 MWh |
PLN 299,025,631 |
Installed capacity ˂1 MW |
8,190,000 MWh |
PLN 5,280,863,522 |
Installed capacity ˂1 MW |
4,725,000 MWh |
PLN 2,182,908,687 |
Capacity utilisation rate >3,504 MWh/MW per year |
10,500,000 MWh |
PLN 5,423,952,758 |
Capacity utilisation rate >3,504 MWh/MW per year |
540,000 MWh |
PLN 305,387,878 |
Installed capacity >1 MW |
3,510,000 MWh |
PLN 1,972,413,921 |
Installed capacity >1 MW |
5,175,000 MWh |
PLN 1,972,413,921 |
The government expects to see new capacities as a result of the new regulations types of installation:
Auctions will be aimed at existing biogas installations at landfills, biomass firing installations and small-scale hydropower plants. The focus is on those categories of renewable energy installation among which there is a high supply of projects (and therefore a high level of competition).
In 2017, auctions should follow the order set out below.
Installations |
---|
Capacity utilisation rate >3,504 MWh/MW per year |
Capacity utilisation rate >3,504 MWh/MW per year |
Installed capacity ˂1 MW |
Capacity utilisation rate >3,504 MWh/MW per year |
Installations |
---|
Installed capacity >1 MW |
Capacity utilisation rate >3,504 MWh/MW per year |
Capacity utilisation rate >3,504 MWh/MW per year |
Capacity utilisation rate >3,504 MWh/MW per year |
Capacity utilisation rate >3,504 MWh/MW per year |
Installed capacity ˂1 MW |
Installed capacity >1 MW |
Installed capacity >1 MW |
Video
Recent cases and judgments have shone a light on some emerging themes and trends that companies will want to consider as part of their risk management framework.
Publication
After a lacklustre finish to 2022 when compared to the vintage year for M&A that was 2021, dealmakers expected 2023 to see the market continue to cool in most sectors, in response to the economic headwinds of rising inflation (with its corresponding impact on financing costs), declining market valuations, tightening regulatory scrutiny and increasing geopolitical tensions.
Publication
On 18 September 2023, the CMA published its Initial Report (Initial Report) on AI Foundation Models (FM), supplemented in April 2024 with the publication of its “Update Paper” focused on potential antitrust risks associated with FMs and a “Technical Update Report” providing more detail on the development on FMs (collectively the “Reports”). Below, we consider these CMA publications.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2023