
Publication
Blue Bonds: Making a splash in the Capital Markets
In 2018, the Republic of Seychelles launched the first-ever “blue bond”, with the support of the World Bank Group and the Global Environment Facility.
Australia | Publication | May 2021
This article was co-authored with Ann Matthias.
The extension to construction working hours implemented by the NSW Government last year in response to the COVID-19 pandemic will be revoked on 7 June 2021. The extension, which was enacted via the Environmental Planning and Assessment (COVID-19 Development – Construction Work Days) Order 2020 (NSW), permitted all building work and demolition work subject to a development consent to be carried out on a Saturday, Sunday or public holiday without the need for approval (subject to conditions). The revocation of the extension means that construction working hours will return to their pre-pandemic settings; contractors will need to comply with conditions on the development consent that restrict the hours of work on a Saturday, Sunday or public holiday, or seek approval under the Environmental Planning and Assessment Act 1979 (NSW) for any change to those hours.
This reverses the previous extension up to 31 March 2022 that was introduced via the COVID-19 Recovery Act 2021 (NSW) (see our update on this here).
We note that the revocation does not apply to the Environmental Planning and Assessment (COVID-19 Development—Infrastructure Construction Work Days No. 2) Order 2020 (NSW) which applies to infrastructure work that is subject to:
Subject to any further changes by the NSW Government, the extended infrastructure working hours will continue to apply until 31 March 2022.
Publication
In 2018, the Republic of Seychelles launched the first-ever “blue bond”, with the support of the World Bank Group and the Global Environment Facility.
Publication
We are delighted to be participating in Marine Money Week New York 2025. As one of the landmark events for the global shipping finance community, and with the global shipping and maritime industry at such a pivotal juncture, we look forward to catching up with clients and contacts to continue discussions around navigating the current challenges and opportunities.
Publication
On 8 May 2025, the Court of Justice of the European Union (the CJEU) delivered its ruling in case C-581/23 (the Ruling), providing guidance on one of the conditions for an exclusive distribution agreement to benefit from the block exemption under Article 4(b)(i) of the 2010 Vertical Block Exemption Regulation (the VBER)1, notably the so-called ‘parallel imposition requirement’.
Subscribe and stay up to date with the latest legal news, information and events . . .
© Norton Rose Fulbright LLP 2025